Abstract:Research purposes: With more and more new highways overpassing the existing railway tunnels,it is necessary to carefully consider the multifaceted influences of the highway on the additional displacement,the additional stress and the regularity of the existing railway tunnel. The dynamic effect of the construction should also be considered. With the theoretical solution, it is difficult to consider the complex terrain and dynamic construction process. Combined with the construction of the highway overpassing the the railway tunnel of the Ganzhou-Longyan Railway in the Xinzhanbei Road in the new district of Shanghang County,the three dimensional finite element was used to analyze the influence of the highway construction on the railway tunnel in order to guide the engineering design and provide the references to the similar projects.
Research conclusions: From the research on the actual terrain condition and the 3D FEM model for the design of the tunnel lining, it was seen the maximum additional displacement of the railway tunnel was about lmm, the maximum additional stress of the tunnel was 1810 kN*m/m and the maximum horizontal displacement of the highway excavation face was about 41.0mm. On the premise of well doing the works of construction organization and monitoring, the safe operation of the railway could be archived. It was also proposed that the excavation could be symmetrically conducted section by section,zone by zone and layer by layer and the appropriate adjustments of the construction procedures could be made according to the monitoring data to further reduce adverse effect on the tunnel.
姚捷. 新建公路施工对赣龙铁路隧道的影响分析[J]. 铁道工程学报, 2013, 30(2): 81-85.
YAO Jie. Analysis of Influence of New Highway Construction on Tunnel of Ganzhou-Longyan Railway. 铁道工程学报, 2013, 30(2): 81-85.
[1] 铁道综合技术研究所.近接隧道施工的设计与指南[M],日本:铁道综合技术研究所,1987. Japan Railway Technical Research institute. Design and Guide for Close-spaced Tunnels [M]. Japan: Japan Railway Technical Research Institute, 1987.
[2] TB 10003—2005,铁路隧道设计规范[S]. TB 10003—2005, Code for Design of Railway Tunnel [S].
[3] 李宁.赣州至龙岩铁路扩能改造工程施工图[Z].武汉:中铁第四勘察设计院集团有限公司,2010. Li Ning. Ganzhou to Longyan Railway Expansion Renovation Project Construction Drawing [Z]. Wuhan: China Railway Siyuan Survey and Design Group Co. Ltd, 2010.
[4] 福建岩土工程勘察研究院.上杭赣龙复线古田北站新站北路(K0+000~K0+400)工程地质勘察报告[R]?福州:福建岩土工程勘察研究院,2012. Fujian Research Institute of Geotechnical Engineering Investigation. Geological Investigation Report for Xinzhanbei Road in Gutian North Station in Ganlong Line in Shanghang County(K0+000~K0+400) [R]. Fuzhou: Fujian Research Institute of Geotechnical Engineering Investigation ,2012.
[5] 张继周,缪林昌.岩土参数概率分布类型及其选择标准[J]. 岩石力学与工程学报, 2009(S2): 3526-3532. Zhang Jizhou,Miao Linchang. Types and Selection Criteria of Probability Distribution of Rock and Soil Parameters [J]. Chinese Journal of Rock Mechanics and Engineering, 2009(S2): 3526-3532.
[6] 铁道第二勘察设计院.铁路工程设计技术手册?隧道[K].北京:中国铁道出版社,1999. Second Railway Survey and Design Institute. Railway Engineering Technology Manual: Tunnel [K]. Beijing: China Railway Publishing House, 1999.
[7] 王齐林,陈静曦,柯鹏振.基于ANSYS的铁路隧道开挖过程三维仿真分析[J].岩土工程界, 2007(1): 52-54. Wang Qilin,Chen Jingxi,Ke Pengzhen. 3-Dimensional Simulation for Railway Tunnel Excavation Process Based on Ansys [J]. Geotechnical Engineering World,2007(1): 52-54.
[8] Phienwej N. Ground Movements in Shield Tunneling in Bangkok Soils [C]//Proc. of the Fourteenth International Conference on Soil Mechanical and Foundation Engineering. Hamburg, 1997.
[9] Zhou Xiaowen, NG C W W. Analytical Solution for Estimating Surface Settlements Induced by Multiple Tunnel Excavation [J]. Chinese Journal of Geotechnical Engineering, 2007(11): 1703-1710.
[10] 何伟奇,何亚伯,王玉泽.道/隧上下交叉段隧道支护分析和加固探讨[J].铁道工程学报, 2011(6): 58-63. He Weiqi,He Yabo,Wang Yuze. Analysis of Tunnel Support and Reinforcement in Intersection of Corridor and Tunnel [J]. Journal of Railway Engineering Society, 2011(6): 58-63.
[11] 郑宝才,程文斌,胡国伟.浅埋暗挖法施工近接交叉地铁 隧道地表沉降监测分析[J].铁道工程学报,2009(1): 72-76. Zheng Baocai,Cheng Wenbin, Hu Guowei. Analysis and Monitoring of Ground Subsidence Caused by Excavation of Adjacent on Crossing Metro Tunnel with Shallow -depth and Subsurface Excavation Method [J]. Journal of Railway Engineering Society,2009(1): 72-76.