Abstract:Research purposes: The concrete slab structure is widely used in the lining structure of railway and highway tunnels.Under the long-term pressure and load of the surrounding rock of tunnel,the concrete slab structure is often deformed and destructed to endanger the safe operation. The test and research were done on the characteristics of the deformation and damage of the concrete slab structure to forecast the possibility of accidents and provide the in - situ monitoring and prediction way to guarantee the safe service of the structure.
Research conclusions:The test results show that application of the time series analysis method can achieve the high precision of predicting the concrete slab deformation with the linear fitting correlation coefficients of more than 0.93 in all measuring points and the prediction error of less than 10% . So,this forecast model is available and can be used as an effective method for monitoring the lining structure of tunnel.
Xie Xiaoyi,Gong Zhihui,Zhou Guangyi. Model Test on Lining of Single Arch Large Cross-section Highway Tunnel to Partial Press[J].Journal of Hunan University of Arts and Science ( Natural Science Edition) ,2011( 1) : 90-94.
Wang Zhijie.Bearing Capacity and Collapse Behavior of Steel Fiber Reinforced Concrete Tunnel Lining[J]. Journal of Railway Science and Engineering,2007 ( 6) : 40-43.
Xang Yuqiang,Tang Guobin,Zhu Hanhua,etc. Failure Mechanism Analysis of Bottom Plate of Prestressed Concrete Box Girder Bridge During Construction[J]. China Journal of Highway and Transport,2010 ( 5 ) : 70-75.
Dong Chengquan,Meng Juntao. Experimental Research and Application on Predicting Rock Mass Failure by Acoustic Emission[J]. West-China Exploration Engineering,2010( 10) : 30-32.
Xiao Wuquan,Leng Wuming.Methods of Time Series Dynamic Prediction of Road Embankment Settlement [J].Journal of Railway Engineering Society,2004(4) :50 - 53.