CONSTRUCTION TECHNIQUE OF ASSEMBLY RIGID FRAME ARCH BY LATERAL SLIDING OF LONGITUDINAL SUPPORT |
SUN Zhangzhi |
Thirteenth Railway Engineering Bureau of MOR |
|
|
Abstract There was no example to proceed the assembly of rigid frame archs by using the method of lateral sliding of the long-span longintudinal support in deep water. During the construction of a major bridge on the Anli Reservoir,this method was applied successfully to complete the assembly of 4 rigid frame arches with 45m span each. The construction works proceeded with rapid speed thigh quality and low cost. The paper introduces this construction method emphatically.
|
Received: 12 January 1998
|
|
|
|
|
|
|
|