Abstract:The statistic analyses on practically measured settlement data for the embankments with soft roadbed have been put forward. The amount of settlement after construction and the change of the speed of settlement are forecasted. At the same time, the author analyses the factors which influence the settlement after construction as follows: the settlement of the main body of embankment. the different periods of construction, and the soft soil layers beneath the consolidated laver of the soft roadbed.
顾湘生. 京九铁路孔垄至九江软基路堤工后沉降及分析[J]. 铁道工程学报, 1999, 16(4): 81-85.
GU Xiang—sheng. SETTLEMENT AFTER CONSTRUCTION OF EMBANKMENT WITH SOFT ROADBED IN KONGLONG-JIUJIANG SECTION OF JING-JIU RAILWAY AND ITS ANALYSES. Journal of Railway Engineering Society, 1999, 16(4): 81-85.