Abstract:Research purposes: The transition section is a joint section between rigid abutment or other structures and flexible embankment and it is a mutant of plastic deformation and rigidity in structure.So during the construction,the measures must be taken for reducing the plastic deformation difference between them,to control post—construction settlement and to achieve smooth transition.Combination of the relevant transition section of Pre—station Bidding IV of Shanghai—Nanjing intercity railway,this paper analyzes the observed data on the settlements during construction and after construction,and summarizes the settlement law.
Research conclusions: Using graded gravel to reinforce the transition section,the total amount of settlement is not large with a regular pattern.The largest amount of settlement of the transition section OCCUrs at the area where is 10—20 m away from structures,and the amount of settlement is proportional to filling height,and the settlement velocity is in the positive correlation with filling time.With the”heaped loading and pre—pressing”after construction.the overall settlement tends to steady state.
李明华,王会乾,蔡理平. 沪宁城际铁路桥涵过渡段工程沉降观测分析[J]. 铁道工程学报, 2010, 27(7): 38-41.
LI Ming—hua,WANG Hui—qian,CAI Li—ping. Observation and Analysis of Settlement of Transition Section between Railway and Bridge of Shanghai—Nanjing Intercity Railway. 铁道工程学报, 2010, 27(7): 38-41.
Hu Hanbin. Analysis of Operating Characteristics of Rail Transition under Dynamic Loading [J ]. Water Resources & Hydropower Information, 2008(8): 43 - 44.
Luo Qiang, ect. The Research of Technical Treatment Measures of Transition Section of High -speed Railway [J]. Journal of Railway Engineering Society, 1999(3): 30 -33.
[3] 李永华.高速铁路桥涵过渡段施工技术[J].科技之友, 2008(5): 50 -52.
Li YongHua. The Construction Technology of Transition Section of High -speed Railway [J]. Light of Science, 2008(5): 50 -52.
Chen Guoyuan, etc. The Comparison Analysis of Settlement Law of Transition Section of Passenger Dedicated Line. [J]. Journal of Central South Forest University, Natural Science, 2008(2): 151 -154.
[7] 徐玲芝.时速200 km /h客运专线过渡段施工技术试验 研究[J].铁道工程学报, 2004(S): 207 -210.
Xu Lingzhi. The Research of Construction Technology of Transition Section of Passenger Dedicated Line at Speed of 120 km /h[J]. Journal of Railway Engineering Society, 2004(S):207 -210.
Qin Dejin, etc. The Construction Technology of Transition Section of Passenger Dedicated Line [J ]. Journal of Railway Engineering Society, 2007(S): 108 - 112.
Li Shoupeng, etc. The Filling Technology of Roadbed Graded Gravel Transition Section of High - speed Railway[J]. Exploration Engineering, 2001(2): 108 - 112.
Yang Guangqing, etc. The Technology Analysis of Road - bridge Transition Section of High - speed Railway, [J].Railway Standard Design, 1999(5): 38 -39.