Abstract:Research purposes:There are many existing railways in Benxi railway terminal and it is difficult to upgrade the existing stations because there is the conflict between the existing railway network and the city development plan.Leading Shenyang - dandong Passenger Dedicated Line not only needs to overcome the shortages of the existing terminal,but also needs to consider the city long - term development plan. This paper studies the passenger and freight traffic upgrading scheme for leading the Shenyang - Dandong Passenger Dedicated Line into the Benxi railway terminal and sums up the experience in this field.
Research conclusions:From studying the optional passenger and freight traffic upgrading schemes for leading the Shenyang - Dandong Railway Passenger Line into the Benxi railway terminal,it is concluded the passenger and freight traffic upgrading scheme should consider the factors of the overall terminal planning,the functions and operation quantitis of the existing stations,the surrounding conditions,the economic factor,environmental protection,topographical and geological conditions and the construction risks. The optimal scheme is recommended through the comprehensive comparison of the optional schemes in technical and economical factors. This upgrading scheme can be as the reference to the similar works.
王玉昆. 沈丹客专引入枢纽客货运改建方案的探讨[J]. 铁道工程学报, 2012, 29(12): 90-94.
WANG Yu - kun. Discussion on Passenger and Freight Traffic Upgrading Scheme for Leading Shenyang - Dandong Railway Passenger Lines into Railway Terminal. 铁道工程学报, 2012, 29(12): 90-94.
The Fourth Survey and Design Institute. Railway Engineer Technical Manual - Station and Yard and Terminal [K]. Beijing: China Railway Publishing House,2004.
[6] 刘其斌,马桂贞. 铁路车站及枢纽[M]. 北京: 中国铁道出版社,1997.
Liu Qibin,Ma Guizhen. Railway station and terminal[M]. Beijing: China Railway Press,1997.
Zhu Xiaoning,Bian Yandong. Research on Overall Evaluating Problems about Drawing High - Speed Railway into Hub of Communication[J]. Journal of the China Railway Society,1998( 4) : 20-24.
Zhou Langya. Research on Scheme Choice for Introducing Passenger Dedicated Line into Railway Hub Based Grey Correlation Analysis[D]. Beijing: Beijing Jiaotong University,2006.
Peng Wensheng,Peng Hui.Passenger Station Layout of High - Speed Railway Existing Terminal[J].Journal of Traffle and Transportation Engineering,2004 ( 2) : 62-65.
The Third Railway Survey and Design Institute Group Corporatation. Feasibility Study of Shenyang to Dandong Railway Passenger Dedicated Line ( Station Replies) [Z]. Tianjin: The Third Railway Survey and Design Institute Group Corporatation,2009.
Lv Jianjun.Study on the Scheme of Leading Tianjin -Qinhuangdao Passenger Dedicated Line into Qinshan Area [J].Journal of Railway Engineering Society,2009(2) :10 -12.