Abstract:Research purposes: The relation between the catenary and pantograph of high-speed railway directly influences the railway operation safety. The catenary and pantograph interact each other via the contact wire and registration arm, so their dynamic and static positions and interaction force are crucial to the function of the catenary and pantograph. The deep researches were done on the slope of registration arm, the catenary staggers in straight line and curve, the first dropper position and the relations among them for providing the reference to the optimal design of the catenary of high-speed railway.
Research conclusions: (1) The slope of registration arm relates to the contact wire tension, the first dropper position, the stagger, the span length, the weights of registration arm and clamp, the curve radius and the superelevation of outer rail. (2) From the research presented in this paper, it is concluded when the other main parameters of the catenary are constant, the slope of registration arm of the catenary of 300 km/h or above high-speed railway is not less than 8 degree in straight line section, and in the curve section the slope is not less than 6 degree and the maximum slope is not bigger than 16 degree. (3) To guarantee a good slope of the registration arm, the catenary stagger is ±200 mm in both sections of straight line and curve with large radius, and the distance from the first dropper to the registration point is 5 meter. It can be as the reference to the similar works.
罗健,白裔峰,魏博. 高速铁路接触网定位器坡度问题的深化研究[J]. 铁道工程学报, 2013, 30(1): 76-80.
LUO Jian, BAI Yi-feng, WEI Bo. Deep Study on Slope of Registration Arm of Catenary of High-speed Railway. 铁道工程学报, 2013, 30(1): 76-80.
[1] 于万聚. 高速电气化铁路接触网[M]. 成都:西南交通大学出版社,2002. Yu Wangju. The Overhead Contact Line of High Speed Electric Railway [M]. Chengdu: Southwest Jiaotong University Press, 2002.
[2] [德]基布岭等.电气化铁道接触网[M]. 中铁电气化局集团有限公司译. 北京:中国电力出版社,2003 KieBling, etc. Contact Lines For Electric Railways [M]. China Railway Electrification Bureau Group Limited Company Translated. Beijing: China Electric Power Press, 2003.
[3] 隋延民. 接触网定位器坡度计算及定位安全措施[J]. 铁道工程学报,2011(4) Sui Yanmin. Calculation of Steady Arm Grade and Registration Safety Measures [J]. Journal of Railway Engineering Society, 2011(4).
[4] TB 10020—2009,高速铁路设计规范(试行)[S]. TB 10020—2009, Code for Design of High Speed Railway [S].
[6] TB/T 2073—2010,电气化铁路接触网零部件技术条件[S]. TB/T 2073—2010, General Technical Specification of Fittings for Overhead Contact System in Electrification Railway [S].
[7] TB 10758—2010,高速铁路电力牵引供电工程施工质量验收标准[S]. TB 10758—2010, Acceptance Standards of Traction Power Supply System for High-speed Electric Railways [S].
[8] TB/T 2809—2005,电气化铁道用铜及铜合金接触线[S]. TB/T 2809—2005, Copper and Copper-alloy Contact Wires for Electric Railway [S].
[9] TB/T 3111—2005,电气化铁道用铜及铜合金绞线[S]. TB/T 3111—2005, Stranded Copper and Copper-alloy Conductors for Electric Railway [S].
[10] TB 10009—2005,铁路电力牵引供电设计规范[S]. TB 10009—2005, Design Code of Electric Traction Feeding [S].