Monitoring Deformation of Existing Ground Track of Urban Rail Transit Caused by Under-passing of High-tension Cable Pipeline
MA Xue-mei1, WU Feng-bo2
1.Beijing Urban Construction Exploration & Surveying Design Research Institute Co. Ltd., Beijing 100101, China;2.Chinese Academy of Sciences, Beijing 100029, China
Abstract:Research purposes:The project of large diameter under-passing the existing ground track of urban rail transit faces the large engineering risks. The strict monitoring should be conducted to the existing ground track in order to guarantee the engineering going on smoothly and the traffic safety of the existing track. This paper mainly introduces monitoring the deformation of the existing ground track caused by the under-passing of pipelines for providing the reference to the similar works.
Research conclusions:Affected by the under-passing of the pipelines, the roadbed of the existing track experienced the process of apparent settlement during construction, apparent post-construction settlement, settlement becoming slow and settlement becoming stable. As the roadbed settlement was large and the rail settlement increased relatively, the rail was uplifted necessarily. The track geometric deformation and rail displacement were small and didn't exceed the control values. Affected by soil disturbances and the seasonal change of the groundwater level, the structure of Shangdi Bridge near the engineering site floated and the differential settlement between the Bridge and the roadbed increased. The attention would be paid to the influence of the back fill soil and ground water on the bridge.
Ma Zhenhai, Yu Chunhua. Analysis of Necessity of the Primary Structural Transmutation Observation in Subways[J]. Journal of Railway Engineering Society, 2008(8): 93-95.
Jin Huai, W u Fengbo, Ma Xuemei etc. Monitoring Measurement and Safety Analysis for Construction of Tunnel Beneath Passenger Transferring Subway Station in Beijing[J]. Journal of Engineering Geology, 2009(5): 703-710.
Ma Xuemei, Wu Fengbo, Ren Gan. Deformation Characteristics of the SNWTP Main Canal Tunnel Short-distance under Existing Subway Station[J]. Geotechnical Engineering World, 2009(9): 71-75.
Bao Yongliang, Zheng Qizhen, Tang Jianzhong. Monitoring Analysis of Construction for Connecting Aisle in Metro Tunnel with Freezing Method[J]. Journal of Railway Engineering Society, 2009(3): 93-96.
[ 6 ] GB 50308—2008, 城市轨道交通工程测量规范[S].
GB 50308—2008, Code for Urban Rail Transit Engineering Survey[S].
[ 7 ] JGJ 8—2007,建筑变形测量规范[S].
JGJ 8—2007, Code for Deformation Measurement of Building and Structure[S].
Qin Changli. The Development of Engineering Surveying Ininfo-engineering Surveying Strategy[J]. Geotechnical Investigation & Surveying,2009(12): 11-16.