Abstract:This paper gives an introduction to those of main process flow, new technique, new workmanship, new construction machinery and instruments, allowable error of construction and test technology adopted in construction of over- head contact line on Chinese first passenger dedicated line of electrification railway with speed up to 200-300 km/h, for reference to the similar construction.
喻军,鲁海祥,张华. 秦沈客运专线接触网施工新技术[J]. 铁道工程学报, 2004, 21(3): 58-61.
YU Jun,LU Hai-yang,ZHANG Hua. NEW CONSTRUCTION TECHNIQUE FOR OVER -HEAD CON- TACT LINE ON QINHUANGDAO-SHENYANG PASSENGER DED- ICATED RAILWAY LINE. 铁道工程学报, 2004, 21(3): 58-61.