Abstract:Research purposes:In order to guide the survey and railway alignment in the goaf region,the basic procedures of the railway survey and alignment are summarized,and the computing method for the safety distance in the goaf,the relative parameter and standard and the way for railway alignment are presented.
Research conclusions:The study shows the boundary angle should be used for calculating the safety distance for high -speed railway and the passenger dedicated line of ballastless track,and the rock displacement angle should be used for calculating the safety distance for normal speed railway. Moreover,combined with engineering examples,the method and way for the railway alignment in goaf are presented,including the comparison and selection of the railway alignments in the periphery of mining area,local optimization of alignment in the mining area and the railway alignment based on calculation and monitoring of the deformation of goal .
State Bureau of coal industry.Rules for Coal Pillars Reserving and Mining Coal under Buildings,Water, Railroad,Main Roadway and Shaft[M].Beijing: Coal Industry Press,2000.
[2]铁道第一勘察设计院.铁路工程地质手册[K]. 北京: 中国铁道出版社,1999.
The First Railway Survey and Design Institute. Handbook of Railway Engineering Geology[K]. Beijing: China Railway Publishing House,1999.
[3]TB 10001—2005,铁路路基设计规范[S].
TB 10001—2005,Code for Design of Railway Subgrade [S].
[4]TB 10621—2009,高速铁路设计规范(试行) [S].
TB 10621—2009,Code for Design of High Speed Railway[S].
Chen Zelian.Research on Influence of the Displacement of Surface Rock in Coal Mine Goaf on High - speed Railway[J].Journal of Railway Engineering Society, 2009(4) : 5-8.