Comprehensive Analysis of Track Joining Scheme of Release Line of Dalian Metro Depot |
ZHANG Peng |
The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251, China |
|
|
Abstract Research purposes: Taking the track joining scheme of release line of Dalian Metro Depot of the first stage project of Dalian metro line 2 as an example, the comprehensive analysis of the track joining are made for the purposes of optimizing the scheme and showing how to make the analyses of it based on the urban planning, land form conditions, line directions, depot location and form and location of the station as well as design principles and technical standards, so as to solve the difficult problems in track joining under different conditions.
Research conclusions: The release line should be located at terminal or reentry stations following by the principle of convenience, reducing the running time of empty train and operating costs. That is to say the rational choice of track joining scheme should be conducted after making the analysis of depot, line conditions, vehicle conditions and the joining condition from economical and technical points of view.
|
Received: 26 November 2007
|
|
|
|
|
[1]GB 50157-2003,地铁设计规范[S].
[2]施仲衡,张弥,等.地下铁道设计与施工[M].西安:陕西科学技术出版社,2002.
[3]铁道第三勘察设计院集团有限公司.大连市地铁2号线一期工程可行性研究报告[R].大连: 2007.
[4]蔺增良.地铁辅助线设计研究[J].都市快速交通,2007(4):63-66.
|
|
|
|