Abstract Research purposes:The temporary consolidation at top piers is regarded as rigid body in continuous girder cantilever construction. And the calculation theory and method are mature. Whereas, temporary consolidation beside piers should be regarded as elastic body. And the calculation methods about it are insufficient. Through the mechanical analysis of temporary consolidation beside piers, a simple calculation method is proposed and can be applied in various construction conditions.Research conclusions:(1) Simplify the temporary consolidation beside piers as elastic three fulcrums model which is consistent with practical force-baring conditions. (2) Calculation method based on elastic three fulcrums model can be well applied in various construction conditions. (3) Calculation of axial forces temporary consolidation beside piers is well related to their tension-compression stiffness, and we should choose calculation formula based on their tension-compression stiffness and force-baring conditions. (4) The calculation method proposed can be the base and accordance for design of temporary consolidation beside piers in PC cantilever casting girders.
|
Received: 21 April 2014
|
|
|
|
|
[1] 丁东. 连续梁悬臂施工临时固结设计与检算[J]. 城市道桥与防洪,2013(7):222-223. Ding Dong. Design and Computation of Temporary Consolidation for Cantilever Construction of Continuous Beam[J]. Urban Roads Bridges & Flood Control,2013(7):222-223. [2] 段钢明.悬臂法施工连续梁临时固结体系的设计与优化[J].山西建筑,2010(31):325-326. Duan Gangming.On Design and Optimization of Temporary Consolidation System of Continuous Beam with Cantilever Method[J].Shanxi Architecture,2010(31):325-326. [3] 王广生,甄玉杰,冯云成. 苏丹西纳公路大桥墩梁临时固结设计与计算[J]. 中外公路,2012(4):174-177. Wang Guangsheng,Zhen Yujie,Feng Yuncheng. Design and Computation of Temporary Consolidation for Beam of Xina Road Bridge in Sudan[J]. Journal of China & Foreign Highway,2012(4):174-177. [4] 张文学,黄荐,刘海陆. 预应力混凝土连续箱梁桥悬臂施工临时固接结构设计[J]. 公路交通科技,2013(2):55-58. Zhang Wenxue, Huang Jian, Liu Hailu. Design of Temporary Fixing Structure for Construction of Prestressed Concrete Continuous Box Girder Bridge Cantilever [J].Journal of Highway and Transportation Research and Development,2013(2):55-58. [5] 卢勇.东江四桥主桥连续梁临时支墩、支座的设计与施工[J].铁道建筑技术,2004(4):27-28. Lu Yong. Design and Construction of Temporary Rest Pier and Bearing for Continuous Beam of Dongjiang Bridge[J]. Railway Construction Technology,2004(4):27-28. [6] 胡向东,周合燊. 悬浇箱梁“临时支撑”设计与计算[J].水运工程,2004(6):14-16. Hu Xiangdong, Zhou Heshen.Design Calculation of "Temporary Support" for Suspendingly Cast Box Girder[J]. Port & Waterway Engineering,2004(6):14-16. [7] 陈建峰,李慧君,袁明,等. 非对称连续梁桥设计与施工[J]. 铁道工程学报,2006(9):31-35. Chen Jianfeng, Li Huijun, Yuan Ming,etc. Design and Construction of Asymmetric Continuous Beam Bridge[J]. Journal of Railway Engineering Society,2006(9):31-35. [8] 丁键,胡成. PC梁桥悬臂浇筑临时支撑的分析研究[J]. 安徽建筑工业学院学报(自然科学版),2010(6):18-21. Ding Jian, Hu Cheng. Computation and Analysis on Temporary Support for the Cantilever Casting Prestressed Concrete Beam Bridge[J]. Journal of Anhui Institute of Architecture & Industry(Natural Science),2010(6):18-21. [9] 董立功. PC连续箱梁悬臂施工支撑式临时固结的计算分析[J]. 现代交通技术.2009,6(1):65~67. Dong Ligong.Computation and Analysis on Supported Temporary Anchor Pier for the Prestressed Concrete Continuous Box Girder Cantilever Construction[J]. Modern Transportation Technology,2009(1):65-67. [10]赵志军. 高速铁路先拱后梁法提篮拱桥设计研究[J]. 铁道工程学报,2013(12):41-45. Zhao Zhijun. Design and Research on Basket Handle Arch Bridge by Method of Arch First and Beam Late in High-speed Railway[J]. Journal of Railway Engineering Society,2013(12):41-45. |
|
|
|