研究目的:为解决《铁路隧道风险评估及管理暂行规定》和《地铁及地下工程建设风险管理指南》在使用 中的困难,找出满足要求且简单、可操作性强的评估方法。
研究结论:(1)经计算表明,在深圳地铁一号线百货广场处桩基主动托换的各风险因素中,施工图设计阶 段的风险、截桩风险及用千斤顶预顶的风险较大.施工场地环境风险和其它不可抗力因素风险相对较小;(2) 得尔菲法与层次分析法相结合可以得到半定量的分析结果,计算精度可以满足《铁路隧道风险评估及管理暂 行规定》和《地铁及地下工程建设风险管理指南》中对风险评估的要求;(3)得尔菲法与层次分析法相结合适 用于简单工程或者复杂工程单个工点的风险评估,同时也适用于复杂工程的风险识别。
Research purposes: In order to resolve the difficulties in using”Interim Rules of Risk Evaluating and Management on Railway Tunnels" and”Guideline of Risk Management for Construction of Subway and Underground Works",this paper finds out a risk analysis method with simple used and maneuverability.
Research conclusions :(1)The result indicates that the risks of working drawing design, piling cut and pre-jack are greater than the ones of construction conditions and others.(2)The method of De1Phi uniting AHP could get the half-quantity result, which could meet the requests of”Interim Rules of Risk Evaluating and Management on Railway Tunnels" and "Guideline of Risk Management for Construction of Subway and Underground Works".( 3 ) 1'he method of De1Phi uniting AHP holds true for risk evaluating of simple works and risk identity of complex projects.