Abstract:Research purposes:Loess exists widely in the area along the Zhengzhou-Xi'an Passenger Dedicated Line, with length of collapsible loess section accounting for 65% of the total railway length. The collapsible loess covers all types of loess in China, with degrees from Grade Ⅰ to Grade Ⅳ. Construction of high-speed railway in such a area with complex geological condition faced the much uncertainty and challenges Therefore, at the early stage of construction, the soaking tests were done in the typical test pits according to the different topographical features of the loess plateau, the second-order terraces of Yi River and Luo River, the loess tableland, the second-order terraces of the Yellow River and the Wei River, so as to seek the influence range of collapsible loess under condition of soaking in large floor for the purpose of providing the tested data for foundation treatment and design of water control and drainage.
Research conclusions:The tests and researches showed the saturation-line rates of 8 soaking test fields under fully soaking were between 1.3~6.0. The horizontal distance between the area where the collapsible deformation happened and the side of soaking test pit increased gradually to 6-15 m from east to west out of the test pit of 15 mm. The horizontal distance between the area where the water proof measures were taken and the shoulder was 0.2~0.5 times of the loess layers' thickness. The design depths were 0.32H -1.60a, 1.53H-3.40a and 0.88H-1.75a separately for the areas of DK 233-DK 250, DK 250 -DK 321 and DK 321-DK 356.
米维军;熊治文;屈耀辉;武小鹏;魏永梁. 郑西铁路客运专线路基防排水技术研究[J]. 铁道工程学报, 2010, 27(5): 4-8.
MI Wei-jun, XIONG Zhi-wen, QU Yao-hui, WU Xiao-peng, WEI Yong-liang. Research on Technology of Water Control and Drainage for Subgrade of Zhengzhou-Xi'an Passenger Dedicated Line. 铁道工程学报, 2010, 27(5): 4-8.
China Railway Fourth Survey and Design Institute. General Geological Description for Preliminary Design of Zhengzhou-Xi'an Passenger Dedicated Line[Z]. Wuhan: China Railway Fourth Survey and Design Institute, 2005.
Qian Zhengyu. New Processes of Construction Technology of Collapsible Loess for Zhengzhou-Xi'an Passenger Dedicated Line[J]. Journal of Railway Engineering Society, 2008(Supplement 1): 71-79.
Wang Xiaojun, Xiong Zhiwen, Chu Huadong, etc. The Research Report on Collapsible Loess Foundation Characteristics and Design Parameters for Zhengzhou-Xi' an Passenger Dedicated Line[R]. Lanzhou: Northwest Research Institute Co. Ltd of China Railway Engineering Corporation, 2009.
Xie Dingyi. The Basic Know ledge of Loess, Loess Mechanics and Loess Engineering Problem Research for Half A Century[Z]. Beijing: The Chinese Society of Rock Mechanics and Engineering, 2007.
Wang Xiaojun. Study on The Great and Important Engineering Geological Problems for Highspeed Railway Construction in Loess Area(Illustrated with Zhengzhou-Xi'an Passenger Dedicated Line)[D]. Lanzhou: Lanzhou University, 2008.
[ 8 ] GB 50025—2004, 湿陷性黄土地区建筑规范[S].
GB 50025—2004, Code for Building Construction in Collapsible Loess Regions[S].
[ 9 ] 关文章. 湿陷性黄土工程性能新篇[M]. 西安: 西安交通大学出版社, 1990.
Guan Wenzhang. The New Facts of Project Performance of Collapsible Loess [M]. Xi'an: Xi'an Jiaotong University Press, 1990.