Abstract:Research purposes: The complexity,risk and harm degrees of large water - filled and no water - filled karst cavities encountered in construction of Yichang -Wanzhou Railway are very rare,and the treatment of them is also very difficult. This paper summarizes the rare experience of treating the large karst cavity of Yichang -Wanzhou Railway for providing the references and improving the work.
Research conclusions: The design concept and construction requirements of large cavity in tunnel are largely different from the tunnel in other places. The crossing rationality,the stability of fundament,the safety of structure and the feasibility of construction must be considered specially. There must be no any hidden trouble. The morphological features of cavity and the fillings must be checked out and meanwhile,the related karst geological condition and hydrogeological condition must be explored gradually. And after,the success can be achieved by taking the relative measures.
邓谊明. 宜万铁路大型岩溶洞穴发育特征及整治[J]. 铁道工程学报, 2011, 28(4): 58-66.
DENG Yi - ming. Developmental Characteristics and Treatment of Large Karst Cavity of Yichang - Wanzhou Railway. 铁道工程学报, 2011, 28(4): 58-66.
Deng Yiming. Related Hydro - geological Analysis of Water Burst in Maluqing Tunnel of Yichang -Wanzhou Railway[J]. Subgrade Engineering, 2010( S) : 26 - 30.
Deng Yiming. The Geological Analysis of Underground Water Burst in Bieyanchou Tunnel at the DK 406 + 422 of Yichang -Wanzhou Railway[J]. Journal of Railway Engineering Society, 2008( 1) : 62 - 65.
[5] 中科院地科所岩溶研究组. 中国岩溶研究[M]. 北京: 科学出版社, 1987.
The Karst Study Room of Geoscience in the Chinese Academy of Sciences . The Study of Karst in China[M]. Beijing: Science Press, 1987.
Deng Yiming,Du Wenshan. Hydrogeology Problems Related to Trough Valiey, Kastic Water and Subterranean Flow in Deshengchang of Qiyushan Tunnel[J]. Journal of Railway Engineering Society,2005( 2) : 12 - 16.