Abstract:Research purposes: The information of risk management research is limited. And the risk management system has not been formed. So it is important and significative to establish the risk prediction and evaluation theory and realize the risk prevention and management for the railway embankment. This paper studied the method of risk prediction and evaluation theory for railway embankment, and analyzed the risk of one railway embankment. All above can provide reference and guidance for the research of risk management techniques of railway subgrade engineering.
Research conclusions: (1) In the paper, a comprehensive analysis method with “analytic hierarchy process + expert investigation + fuzzy evaluation" is put forward for analysis and calculation of the risk of railway embankment engineering and the specific steps have been given. (2)It is suggested to class risk factors of railway embankment as slight degree, mild degree, moderate degree, severe degree and catastrophic degree and the corresponding treatment measures are put forward. (3)The calculation result shows the weight of seismic risk factor is maximum in the risk factors, therefore, the corresponding risk treatment measures shall be taken in the design of embankment in the seismic area.(4)The comprehensive analysis method with “analytic hierarchy process + expert investigation + fuzzy evaluation” is characterized by distinct levels,clear steps and quantitative analysis of risk, which can be used for identification and analysis of subgrade engineering risk of railway and highway.
魏永幸,丁兆锋,罗一农. 铁路路堤风险管理研究与实例分析[J]. 铁道工程学报, 2013, 30(9): 121-126.
WEI Yong-xing, DING Zhao-feng, LUO Yi-nong. Risk Management Research and Case Analysis for Embankment of Railway. Journal of Railway Engineering Society, 2013, 30(9): 121-126.
Wen Jiahong. Mainstreaming Disaster Risk Management in China[J]. Progress in Geography, 2010(7):771-777.
[2]郭坚鸽.赣龙扩能施工图设计路基风险评估探讨[J].铁道勘察, 2012(3):38-41.
Guo Jiange. Discuss Risk Assessment Of Roadbed About Capacity Enlargement Construction Drawing Design of Ganzhou-Longyan Railway[J]. Railway Investigation and Surveying, 2012(3):38-41.
[3]袁腾方高速公路岩溶路基稳定性风险分析方法[J].铁道工程学报, 2010(4):61-66.
Yuan Tengfang. Risk Analysis Method of Carst Roadbed Stability in Expressway[J]. Journal of Railway Engineering Society, 2010(4):61-66.
Chen Guojun. Application of Fuzzy Compressive Evaluation in the Grading of Hazard in Xinbin County, Liaoning Province[J]. Geology and Resources, 2009(1):74-76.
[8]吕云南.市政道路工程质量模糊综合评价[J].武汉理工大学学报, 2000(6):34-38.
Lv Yunnan. Fuzzy Compressive Evaluation for the Quality of Municipal Road[J]. Journal of Wuhan University of Technology, 2000(6):34-38.
Zhang Liping. Fuzzy Comprehensive Evaluation on Disastrous Degree of Mine Debris Flow-Taking Shenfu-Dongsheng Coal Field as Example[J]. Journal of Mountain Research, 2002(2):212-217.