MECHANISM AND PRACTICE ON REINFORCING LOOSE BED LANDS、 LIDE WITH PRESTRESSED ANCHORING ROPE |
JIANG Zhongxin |
Second Survey and Design Institute,Ministry of Railways,Chengdu 610031 |
|
|
Abstract Based on the test research and engineering practices on reinforcing the loose bed landslide with prestressed anchoring rope (anchor cable) ,the problems concerned with the stress response ,anchoring force ,exhaustion of prestress force and the group of anchoring ropes are explored.The practi?cal engineering applications of reinforcing the landslide and the slope in rock fracture zone , slump-mass and sandy gravel are also expounded in detail in this paper.
(According to research and practice,the following mechanism on reinforcing loose bed landslide and slope are expounded. The regularity of transmission and response of stress is similar in loose bed and in rock bed. The anchoring force in anchoring section loose bed may be strong enough through ex?panding the aperture and grouting in twice times. Exhaustion of pres tress force with compression creep of loose bed is limited and can be compensated. Effect of a group of anchoring rope is regular,as the in?terval of the rope is suitable.
Under some conditions,the engineering of reinforcing landslide and slope in rock fracture zone,slump- mass and sandy gravel is more cheap,high speed and safe with prestressed anchoring rope than anti?slide pile. The Laoyayan landslide of the Baoji-Chengdu railway is a example in which the reinforced loose bed was applied atone with prestressed anchoring rope. Using prestressed anchoring rope for re?inforcing the excavation wall o{ sandy gravel in building of Bank of China is the first time in Chengdu city. The Badu landslide of Nanning-Kunming railway in slump-mass, a main reinforcing engineering in which the prestressed anchoring rope was applied,is a most big controlled landslide in railways.
|
Received: 20 July 1998
|
|
|
|
|
[1]赵德志.松敢介质预应力锚索加固机理研究[D].四 川联合大学硕士学位论文. 1997.
[2]程良奎,玥建林,土层锚杆的几个力学问题[A].岩土 锚固工程技术[M].北京:人民交通出版社.1996;1~6
[3]蒋忠信.加固滑坡的预应力锚索技术[J].山地研究,1996,14(1):58 ~64.
[4]肖昭然,李象范,侯学渊.群锚荷载传递新方法一剪切位移传递函数综合法[A].岩土锚固工程技术[M]. 北京;人民交通出版社,1996:61~66.
[5]李聚金,蒋楚生.预应力锚索技术在滑坡中的应用[J].路基工程,1992,(6): 18~24.
[6]蒋楚生,李聚金.预应力锚索在深基坑护壁工程中的应用[A].岩土锚固工程技术[M].北京;人民交通出 版社,1996:303~305.
[7]李聚金.岩土预应力锚索工程实践[J].路基工程,1996,(3):48-5l,58.
[8]黄俊,蒋忠信,陈宝林.宝成二线老鸦岩隧道山体预应力锚索工程实践[J].路基工程,1997.(1);69~73.
[9]李宇洪.平中2号隧道出口滑坡病害整治[J].路基工程,1997,(5):69 ~73.
|
|
|
|