Prediction of Water-bursting Volume in Karst Tunnel under Different Geological Boundary Conditions |
WU Zhi-sheng |
The Fourth Survey and Design Institute of China Railways, Wuhan, Hubei 430063,China |
|
|
Abstract Research purposes: At present, there are many methods in China of computing the water-bursting volume in karat tunnel. Although there are many methods, but they can rat completely meet the cannel design requirements far computing normal water-bursting volume and max. water-bursting volume with big gaps, so it is necessary to do the researches for the purposes of seeking new way. Research methods: A new method is obtained by adopting inversion derivation with long-term observed data about and surface spring water-bursting volumes in Naming Tunnel, a long shallow buried karat tunnel. Research results: The prediction method of big spring flow and curve inversion analysis method (new balance method) of water-bursting in tunnel are obtained through doing researches, and at the same time, many important hydrological and geological parameters and the ratios of water-bursting volumes in tunnel in different seasons are obtained with long-term observed data, including water-collection area,water-bursting volume in dry season, water-enriching volume for one unit length in dry season and the factor of rain penetrating into tunnel. Research Conclusions: The design and construction concepts on hydrological and geological parameters and sampling water-bursting volume should be changed, and the construction of karat tunnel should be evaluated with scientific development outlook.
|
Received: 13 August 2007
|
|
|
|
|
[1]南岭隧道水文地质特征及涌水量预测的研究[R].武 汉:铁道部第四勘察设计院,1991.
[2]石文慧.南岭隧道岩溶水文地质初步探讨[C ]//周文 辅.中国地质学会第二届岩溶学术会议论文选集.北京: 科学出版社,1982:145-151.
[3]何宇彬.试论喀斯特水特征[J].水文地质工程地质, 1989(4):5-10.
[4]铁道部科学研究院,西南交通大学.既有隧道环境地下 水变化规律以及对环境生态平衡影响的评估[R].1996.
|
|
|
|