Study of Metro Depot Train Test Line Function and Design Requirements |
ZHANG Xiong, LI Jian-hong |
China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan 610031,China |
|
|
Abstract Research purposes: The train test line in metro depot is used for train dynamic debugging and test. New trains and the repaired trains must be debugged and tested on the test line before service operation. The test line should be proper on the length,curve radius,grade , etc , but that is difficult to get , as the restricting of area. It should be emphasis that determine of function requirements and optimizing scheme of test line on the design of metro depot.
Research conclusions: The test line in metro depot is necessary and important to ensure safety and reliability of train operation. The teat line should be designed to meet the highest operation velocity test if site is available. When the site area is restricted, we should propose to determine the test line design standard according to the class of depot, and necessary high velocity teat can be carried out on main line.
|
Received: 01 April 2008
|
|
|
|
|
[1] GB 50157—2003,地铁设计规范[S].
[2] 刘文明.变频调速车辆特性的制约因素及改善特性的途 径[J].城市管理与科技,1999(4):23-27.
[3] 广州地下铁道总公司.广州地铁列车新车调试及验收大 纲[R].广州:广州地下铁道总公司,2006.
[4] 广州地下铁道总公司.广州地铁列车检修规程[R].广 州:广州地下铁道总公司,2006.
|
|
|
|