Analysis ofOptmi ization of Unsupported Cable Force of Steel Frame with Cable Hoisting Method |
HAN Le,i ZHANG Jun-bing |
China Railway NO. 3 Engineering Group Co. Ltd,Taiyuan,Shanxi 030001,China |
|
|
Abstract Research purposes: By summing up the advantages and disadvantages of using the torque balance method and the finite element"zero displacementmethod" to determine the cable force, the optimal calculationmethod isused for the LuobuxiBridge to guarantee the linear accuracy in arch rib segmentof the bridge and construction safety.
Research conclusions:The optimal cable force is solvedwith non -linear iterative calculation and taking the cable and frame structure as an integrated structure. Through the iterative calculation and the calculations for the normal assembly and reverse disassembly of the frame segmen,t the optimal cable force before closure is obtained and the control data about tube stress and elevation of the steel tube frame during hoisting the frame are offered. The application shows this method canmake sure that the steel tube frame has the perfect closure condition and the accurate data aboutelevation can be offered. This is significant to guide hoisting the steel tube frame ofLuobuxiBridge.
|
Received: 29 July 2009
|
|
|
|
|
[1] 周仁忠,陈富强,杨炎华.重庆朝天门长江大桥施工扣索索力监控分析[J].交通科技, 2009(1): 15 -18.
[2] 张克波,王国俊.大跨度钢管混凝土拱桥拱肋吊装中的扣索索力计算[J].长沙理工大学学报, 2005(4): 17 -21.
[3] 陈德伟,范立础.确定预应力混凝土斜拉桥恒载初始索力的方法[J].同济大学学报, 1998(2): 120 -124.
[4] 肖汝成,项海帆.斜拉桥索力优化的影响矩阵法[J].同济大学学报, 1998(3): 235 -240.
[5] 张建民,郑皆连.大跨度钢管混凝土拱桥吊装过程的优化计算方法[J].桥梁建设, 2002(1): 52 -58.
[6] TB 10415)2003,铁路桥涵工程施工质量验收标准[S].
[7] TB 10203)2002,铁路桥涵施工规范[S].
[8] 杨文渊.起重吊装常用数据手册[K].北京:人民交通出版社, 2002.
[9] 交通部第一公路工程总公司.桥涵[M ].北京:人民交通出版社, 2002.
[10]陈宝春.钢管混凝土拱桥[M ].北京:人民交通出版社,2007.
|
|
|
|