Discussion on the Construction Scheme of Tunnel Entrance in Crowded Population Area |
ZHANG Y ing-m ing, DING Li-jin |
Taiyuan -Zhongwei-Yinchuan RailwayConstructionHeadquarter, CCCC TunnelConstruction EngineeringCo. Ltd.,Lvliang, Shanxi 033314, China |
|
|
Abstract Research purposes: Through discussion on the construction scheme of Liulin Tunnel entrance in crowed population area, this paper summarizes the construction experiences of the tunnel entrance, including the construction scheme, construction method, construction measures and caution for attention in construction of the tunnelentrance, for the purpose of providing the reference to the similar works.
Research conclusions:Liulin Tunnel is located in the crowded population area. Successful construction of its entrance shows the construction scheme, construction method and constructionmeasured for the tunnelare economic and feasible.The method and scheme ofadopting short footage, loose blas,t static blas t, small pilot tunnel along with using anchor to spurt the ne t, the steel pipe column to hang the Bruckernetand to laymortar to the slice stone overcome the problems in construction of the tunnel entrance in the steep slope and crowed population area and the problems of synchronic operation for the tunnel connectedwith bridge, andmeet the requirements under special construction condition.
|
Received: 15 August 2009
|
|
|
|
|
[1] TB 10027)2001,铁路工程不良地质勘察规程[S].
[2] TB 10003)2005,铁路隧道设计规范[S].
[3] TB 10108)2002,铁路隧道锚喷构筑法技术规范[S].
[4] TB 10401. 1)2003,铁路工程施工安全技术规程(上册)[S].
[5] TB 10121)2007,铁路隧道监控量测技术规程[S].
[6] TZ 214)2005,客运专线铁路隧道工程施工技术指南[S].
[7] 陈小雄.现代隧道工程理论及隧道施工[M ].成都:西南交通大学出版社, 2006.
[8] 关宝树.隧道工程施工要点集[M ].北京:人民交通出版社, 2003.
[9] 铁道部工程设计鉴定中心.高速铁路隧道[M ].北京:中国铁道出版社, 2006.
[10]申玉生,赵玉光.连拱隧道洞口段地表沉降量测预报及坍方治理[J].现代隧道技术, 2005(4): 60 -61.
|
|
|
|