Construction of Vertical and Cross Subway Tunnel |
LIU Wei-Duo |
China Railway 16th Construction Bureau Ltd, Beijing 100855, China |
|
|
Abstract Research purposes:With more and more cities taking subway as the most effective means of solving the traffic jam, more and more vertical and cross lines in subway tunnels are constructed, and it brings more risks and challenges to the tunnel construction. This paper researches the key points , the difficult points and the measures to be taken for vertical and cross construction so as to provide the reference to the subway tunnel construction.
Research conclusions:The advanced forecast, blasting control, monitoring and measurement are essential to the construction of vertical and cross tunnel, and they are supplementary to each other and not one of them can be dispensed with. To construction of vertical and cross tunnel, the blasting control is key point and the advanced forecast, monitoring and measurement are also important. Only when the real geological condition of the working face is well known through the advanced forecast and the change o f the ground subsidence is well known through them on itored and measured data can the most reasonable and effective blasting control parameters be worked out, the potential risk be eliminated and the smooth construction of vertical and cross tunnel be ensured.
|
Received: 14 July 2009
|
|
|
|
|
[ 1 ] 中铁十六局集团有限公司. 深圳市地铁 3号线少莲区间岩土详细勘察报告 [ R ]. 北京: 中铁十六局集团有限公司, 2008.
China Railway 16th Construction Bureau. Ltd. Investigation report of Shaoniangong Station-Lianhuacun Station's tunnel of Shenzhen 3th line[R]. Beijing: China Railway 16th Construction Bureau. Ltd, 2008.
[ 2 ] 苏自约, 陈谦, 徐祯祥, 等. 中国岩土锚固协会第十五次全国岩土锚固学术研讨会论文集 [ C ]. 北京: 人民交通出版社, 2006.
Su Ziyue, Chen Qian, Xu Zhenxiang, et al. The 15th Learning Conference on Rock-soil Anchoring of China Rock-soil Anchoring Association[C]. Beijing, China Communication Press, 2006.
[ 3 ] GB 50308 1999, 地下铁道、轻轨交通工程测量规范 [S].
GB 50308 1999, Code of Metro and Light Rail Engineering Survey[S].
[ 4 ] GB 50026 93, 工程测量规范 [S].
GB 50026 93, Code for Engineering Surveying[S].
[ 5 ] GB 50299 1999, 地下铁道工程施工及验收规范[S].
GB 50299 1999, Code for Construction and Acceptance of Metro Engineering[S].
[ 6 ] 郑俊杰, 包德勇, 龚彦峰. 铁路隧道下穿既有高速公路隧道施工控制技术研究 [ J]. 铁道工程学报, 2006( 8 ): 80-84.
Zheng Junjie, Bao Deyong , Gong Yanfeng . Research on Construction Control Technology for Railway Tunnel Underneath Passing Exiting Expressway Tunnel [J]. Journal of Railway Engineering Society, 2006(8): 80-84.
[ 7 ] 杨智国. 地质超前预报在桃花浦一号隧道 TBM 施工中的应用 [ J]. 铁道工程学报, 2004( 1): 65- 68.
Yang Zhiguo. Study on Advance Geological Forecast in TBM Construction of NO.1 Taohuapu Tunnel[J]. Journal of Railway Engineering Society, 2004(1): 65- 68 .
[ 8 ] 杨芸. 隧道施工动态监测及其工程应用 [ J]. 贵州工业大学学报 ( 自然科学版 ), 2008( 2): 105- 108.
Yang Yun. Tunnel Construction Dynamic Mo itoring and Its Engineering Application[J]. Journal of Guizhou University(Natural Science Edition), 2008(2): 105- 108 .
[ 9 ] GB 6722 2003, 爆破安全规程[S] .
GB 6722 2003 , Code of Blasting Safety[S].
[ 10 ] 王海亮. 工程爆破 [M] . 北京: 中国铁道出版社, 2008.
Wang Hailiang. Engineering Blasting[M]. Beijing: China Railway Publishing House, 2008 .
|
|
|
|