Study on the CP Ⅲ Vertical Control Network Establishing Method of High—speed Railway Based on Free.—station |
FU Jian—bin1,LIU Cheng—long2,LU Jian—kang3,HE Bo2,YANG xue—feng2 |
1.Construction Management Department of MOR,Beijing 100844,China;2.Southwest Jiaotong University,Chengdu,Sichuan 610031,China;3.China Railway Eryuan Engineering Group Co.Ltd,Chengdu,Sichuan 610031,China |
|
|
Abstract Research purposes: Aiming at the measurement for establishment of high—speed railway track control network CP Ⅲ vertical control network,the paper not only analyzes the technical requirements of CP Ⅲ vertical control network but also the technical features of methods from Germany and China for establishment of vertical control network,and based on the principle of free—station in cPm plane control network,the feasibility of building CP Ⅲ trigonometric leveling net work by the observational values of free—station in CP Ⅲ plane control network is discussed.
Research conclusions:Through the introduction of the middle method of total station,CP Ⅲ trigonometric leveling network is established and compared to the prerequisite for high precision trigonometric leveling,it is considered to be feasible.At the same time,comparison and statistical analysis among actual accuracy index of large mounts of CP Ⅲ trigonometric leveling network data are done,proving that the method proposed in the paper can meet the accuracy;equirements for the second order leveling and CP Ⅲ vertical control network,SO it is a new method in establishing CP Ⅲ vertical control network.
|
Received: 20 October 2010
|
|
|
|
|
[1]铁建设[2006]189号,客运专线无碴轨道铁路工程测量 暂行规定[S].
Railway Construction[2006]No.189, Interim Provisions for Engineering Survey of Passenger—special Ballastless Railway[S].
[2]刘成龙,杨友涛,徐小左.高速铁路CPm交会网必要测 量精度的仿真计算[J].西南交通大学学报,2008(6):
718—723. Liu Chenglong,Yang Youtao,Xu Xiaozuo.Simulated Determination of Accuracy Requirement for Control Points m Intersection Networks in High—speed Railway [J].Journal of Southwest Jiaotong Uniwersity,2008 (6):718-723.
[3] 倪先桃.无砟轨道CP Ⅲ高程控制网测量与数据处理方 法研究[D].成都:西南交通大学,2009.
Ni Xiantao.The Study on Vertical Network Survey and Data—-processing Method of Ballastless Track Base—- Piles CP Ⅲ[D]. Chengdu:Southwest Jiaotong University,2009.
[4]TB 10601--2009,高速铁路工程测量规范[s].
TB 10601—-2009.Code for Engineering Survey of High Speed Railway[S].
[5]GB/T 12897--2006,国家一、二等水准测量规范[S].
GB/T 12897--2006,Specifications for the First and Second Order Leveling[S].
[6] 程昂,刘成龙,徐小左.CP Ⅲ平面网必要点位精度的研究 [J].铁道工程学报,2009(1):44—45.
Cheng Ang,Liu Chenglong,Xu Xiaozuo.Research on the Positional Accuracy Required for CP Ⅲ Network [J].Journal of Railway Engineering Society,2009(1): 44—45.
[7] 徐小左,刘成龙,杨友涛.无砟轨道精调中CP Ⅲ网点稳定 性检测方法的研究[J].铁道工程学报,2008(9):21— 22.
Xu Xiaozuo,Liu Chenglong,Yang Youtao.Research on the Detection Method of CP Ⅲ Points Stabifity in Fine Adjustment of Ballastless Track[J].Journal of Railway Engineering Society,2008(9):21—22.
[8]武汉大学测绘学院一测量平差学科组.误差理论与测量 平差基础[M].武汉:武汉大学出版社,2003.
Subject Group of Sueveying Adjustment,School of Geodesy and Geomaties,Wuhan University.Theory of Errors and Basis of Surveying Adjustment[M]. Wuhan:Wuhan University Press,2003.
|
|
|
|