Overlap Joint of Coordinate System and Design of Track of High—speed Railway |
LI Ya—hui,SHI De—bin,ZHANG Yun—fang |
The Third Railway Survey and Design Institute Group Corporation,Tianjin 30025 1,China |
|
|
Abstract Research purposes: In the jointing area of independent engineering coordinate system of hish—speed railway,the inappropriateness of the coordinate system and track design causes the problem that the central line of track is not be linked up smoothly.Through the comparative analysis,this paper analyzes its reason and offers a solution,which has a directive sense to design of the coordinate system and track.
Research conclusions:Through the analysis of the problem in the jointing area of coordinate system,the following points can be concluded:The projection distortion difference between the adjacent coordinate systems should be controlled reasonably in designing the coordinate system.The control points after transferring the central meridian of coordinate system should be chosen correctly for the design of track.The same control points in different coordinate systems should be transferred by changing the central meridian of coordinate systems.
|
Received: 15 November 2010
|
|
|
|
|
[1]TB 10601—2009,高速铁路工程测量规范[S].
TB 10601--2009,Code for Engineering Survey of High Railway[S].
[2]梅熙.高斯投影变形对高速铁路线路设计的影响[C]//高速铁路精密测量理论及测绘新技术应用国际学术研讨会论文集.成都:西南交通大学出版社,2010.
Mei Xi.Deformation Effect on Route Design of High Speed Railway with Gauss Projection[C]//Proceedingsof the International Symposium on Precision Engineering Survey Theory and Spatial Information Technology for High Speed Railway.Chengdu: Southwest Jiaotong University Press,2010.
[3]孔祥元,梅是义.控制测量学(第二版)[M].武汉:武汉大学出版社,2004.
Kong Xiangyuan,Mei shiyi.Theory of Control Surveying[M].Wuhan:Wuhan University Press,2004.
[4] 宁黎平.高海拔地区铁路施工控制网的建立[J].铁道工程学报,2008(11):18—21.
Sing Liping.The Building of Railway Comtruction Control Network in the High Altitude Area[J].Journal of Railway Engineering Society,2008(11):18— 21.
[5] 张江.坐标转换在铁路勘察设计中的应用探讨[J].铁道勘察,2010(4):11—13.
Zhang Jiang.Discussion on Applications of Coordinate Conversion in Railway Surveying and Design[J].Railway Investigation and Surveying。2010(4):11—13.
[6]赵长胜.高斯投影坐标反算的迭代算法[J].测绘通报,2004(3):16—17.
Zhao Changsheng. Iterative Algorithm of Gauss Projection Plane Rectangular Coordinates[J].Bulletin of Surveying and Mapping。2004(3):16一17.
[7] 徐仕琪,张晓帆,周可法,等.关于利用七参数法进行wGS一84和BJ一54坐标转换问题的探讨[J].测绘与空间地理信息,2007(5):33—42.
Xu Shiqi,Zhang Xiaofan,Zhou Kefa,ete.Discussion of the Seven·-parameter Coordinate Transformation between WGS一84 and BJ一54[J].Geomaties& Spatial Information Technology,2007(5):33-42.
[8] 王解先,邱杨媛.高程误差对七参数转换的影响[J].大地测量与地球动力学,2007(3):25—38.
Wang Jiexian,Qiu Yangyuan.Influence of Ellipsoidal Height Error on Seven—-parameter Transformation [J].Journal of Geodesy and Geodynamies,2007(3):25—38.
[9] 张国祯,杨晓红.GPS测量中坐标系统、坐标系的转换过程[J].测绘与空间地理信息,2009(3):178—179.
Zhang Guozhen,Yang Xiaohong.The Transformation Procedure of Coordinate System in GPS Surveying[J].Geomatics&Spatial Information Technology,2009(3):178一179.
[10]孔祥元,郭际明,刘宗泉.大地测量学基础[M].武汉:武汉大学出版社,2001.
Kong Xiangyuan,Guo Jiming,Liu Zongquan.Foundation of Geodesy[M].Wuhan:Wuhan University Press,2001.
|
|
|
|