Discussion on Program for Building Railway in Plain Channelized Region and the Railway Alignment |
ZHU Jian - nong,GUO Ye - qing,XU Hong - min,GUO Jian - sheng |
Shanghai Design Institute of China Railway Group Ltd,Shanghai 200070,China |
|
|
Abstract Research purposes: The section between Qidong and Nantong of the Nanjing - Qidong Railway is located in Nantong City,Jiangsu Province,along the downstream of the Yangtze River. The region along the railway is the plain channelized region with the dense population,the dense channelization and the developed highway network. With rapid development of regional economy and speeding up the path of urbanization,the demand of transportation is very high.Through analysis of the region features and the orientation of the project functions in the plain channelized region,the principle for the railway alignment is presented and the reasonable construction program is offered.
Research conclusions: The railway alignment in plain channelized region should be connected with the city plan. There are two programs for the railway alignment in this section. One is that the railway is on the south side of the Nanjing -Qingdao Highway and the other is that the railway is on the north side of the highway. For closely connecting with the local plan,making full use of the planed reserved passage,considering the influence of the projects on construction and the planned projects and ensuring the rationality of all projects,the program of the railway on the south side of the highway is recommended. Aiming at the region features that there are lots of houses,channelization networks,passages and there is a little soil resource,soil material and land resource with soft soil spreading widely,the boundaries of the track and bridge should be selected in combination with the geological conditions and the filling height,and the proportion of the bridge should be appropriately increased while the demolition and land occupation should be reduced.From the fields of the project investment,the project difficulty,the transport capacity and adaptability and economic evaluation,the comprehensive comparison of the single track program with double - track program is made. The program of building single track with reserved double - track condition is recommended. In order to cut the difficulty in building the double - track in future,it is proposed the beginning and end key projects of somestations should be set aside.
|
Received: 29 June 2011
|
|
|
|
|
[1] 中铁上海设计院集团有限公司. 新建铁路宁启线南通东至启东段可行性研究[R]. 上海: 中铁上海设计院集团有限公司, 2010.
China Railway Shanghai Design Institute Group Ltd.The Feasibility Study of Nanjing - Qidong Railway Line New Qidong,Nantong,East [R]. Shanghai: China Railway Shanghai Design Institute Limited,2010.
[2] 中铁上海设计院集团有限公司. 新建铁路宁启线南通东至启东段初步设计[R] . 上海: 中铁上海设计院集团有限公司, 2010.
Shanghai Design Institute of China Railway Group Ltd.Nanjing - Qidong Railway Line New Qidong,Nantong,East Section of the Preliminary Design [R]. Shanghai:China Railway Shanghai Design Institute Limited,2010.
[3] GB 50090—2006,铁路线路设计规范[S].
GB 50090—2006,The Railway Line Design Specification[S].
[4] 铁建设[2005]285 号,新建时速200 公里客货共线铁路设计暂行规定[S].
Railway Construction [2005] No. 285,The New 200 km Railway Passenger and Freight Lines Were Designed Interim Provisions [S].
[5] 祝建农,平志斌,等. 宁启铁路增建二线环保选线方案研究[J]. 轨道交通, 2010( 2) : 70 - 72.
Zhu Jiannong,Ping Zhibin, etc. Nanjing - Qidong Railway Additional Second Line Selection Program of Environmental Protection [J]. Rail Transport,2010( 2) : 70 - 72.
[6] 刘春明. 铁路选线应综合考虑的主要问题[J]. 铁道勘察, 2007( 2) : 69 - 72.
Liu Chunming. The Railway Line Selection Should be Considered a Major Problem [J]. Railway Surveys,2007( 2) : 69 - 72.
[7] 李洪斌. 张唐重载铁路的综合选线技术[J]. 铁道工程学报, 2011( 6) : 10 - 13.
Li Hongbin. Zhang Tang Comprehensive Heavy Rail Line Selection Technique [J]. Journal of Railway Engineering,2011( 6) : 10 - 13.
[8] 杨元明. 既有铁路扩能改造若干问题探讨[J]. 铁道工程学报, 2010( 12) : 1 - 6.
Yang Yuanming. The Existing Rail Capacity Expansion of a Number of Issues [J]. Journal of Railway Engineering,2010( 12) : 1 - 6.
[9] 吴伟. 平原及山区高速铁路选线的控制因素[J]. 铁道勘察, 2010( 1) : 87 - 89.
Wu Wei. Plains and Mountains High - speed Railway Line Selection Control Factors [J]. Railway Survey.2010( 1) : 87 - 89.
|
|
|
|