Abstract Research purposes: According to the calculation, this paper analyzed the transient problem of existing double-track tunnel and put forward the reduction measures.
Research methods: Take the double-track tunnel in the Lanzhou-Wunan for example,the relation graph of train speed and maximum pressure has been simulated and figured out with the formula.
Research results: The result of calculation indicates that transient pressure on the tunnel of Shanggulangxia cannot reach the standard of comfort while traveling speed is over 145 km/h.
Research conclusions: With the trains’ being-speed up, the transient pressure of double-track tunnel in the existing railway cannot reach the standard of comfort. In the future construction, we should take active or passive reduction methods according to the specific situation.
|
Received: 07 June 2006
|
|
|
|
|
[2] |
Dayman B and Vardy A. E. Alleviation of tunnel air pressure transients-1 experimental program[A]. proc 3rd Int Symp on the aerodynamics and ventilation of vehicle tunnels[C]. Paper H2, BHRA, Sheffield, UK, March, 1979.
|
[1] |
Fox J. A. and Henson, D. A: The prediction of the magnitudes of Pressure transients generated by a train entering double tunnel Proc[J]. Inst. Civil Eng. 1971(49):53-69.
|
[3] |
王建宇.列车通过隧道时诱发的空气动力学问题和高速铁路隧道设计参数[J].隧道译丛, 1995(1):3-13.
|
|
|
|