Internal Force Analysis of the Curve Obliquity Reinforced Concrete Rigid Frame Continuous Beam Bridge |
CHAI Gui-hong, BAI Hong-guo |
The Third Railway Survey and Design Institute Group Corporation, Tianjin 300142,China |
|
|
Abstract Research purposes: For the peculiar crankle coupling mechanics peculiarity of the curve bridge that the structure internal force is quite intricacy. In the paper the internal force of the curve obliquity reinforced concrete rigid frame continuous beam bridge is discussed as the Beijing South Station Liangshuihe rigid frame continuous beam medium span bridge as the engineering background.
Research conclusions: The crankle coupling and obliquity of the rigid pier made the distortion, the vertical moment are greater than the straight bridge's of the same spans. And the outboard deflection is greater than the inboard one. The support reactions of the curve bridge have a trend that the outboard support reactions are greater than the inboard ones, contrasted with the straight bridge of the same spans.
|
Received: 14 February 2008
|
|
|
|
|
[1] 项海帆.高等桥梁结构理论[M].北京:人民交通出版 社,2001.
[2] TB 10002.1-2005,铁路桥涵设计基本规范[S].
[3] 苏伟,王俊杰.秦沈客运专线刚构连续梁桥设计[J].铁 道标准设计,2001(11):12-14.
[4] 李凤芹,马胜双,王俊杰.客运专线斜交刚构连续梁桥研 究[J].铁道标准设计,2007(2):29-32.
|
|
|
|