Analysis of Plane Layout of Shared Site for Multiple Tracks in Subway Vehicle Depot |
ZHANG Peng, TENG Yi-bi, LAN Shu-gui |
The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251, China |
|
|
Abstract Research purposes:Taking the design plan for the Chuanyanghe Vehicle Base of Shanghai subway as an example, the plane design and optimization are made to the plan for the shared site of three tracks and track joining in Chuanyanghe Vehicle Depot. The plane layout of the vehicle depot is determined according to the urban planning, terrain conditions, alignments, depot location, station style and location and depot’s functional orientation. Through analysis, the way is presented for how to share the site by three tracks to achieve the goal of maximum utilization of resource.
Research conclusions:Through the plane design and optimization made to the shared site of three tracks in the Chuanyanghe Vehicle Base composed of the northern stabling yard of Line 11, southern periodic repair depot for Line 11 and stabling yard of Line 13, the integration of urban plan is improved, the strong points of resource sharing of urban mass transit network and vehicle base are given play to and the construction cost, the floor area of the depot and operation cost are reduced.
|
Received: 10 November 2009
|
|
|
|
|
[ 1 ] GB 50157—2003, 地铁设计规范 [S].
GB 50157—2003, Code for Design of Metro[S].
[ 2 ] GB 50490—2009,城市轨道交通技术规范 [S].
GB 50490—2009, Technical Code of Urban Rail Transit [S].
[ 3 ] TB10501—98,铁路工程环境保护设计规范 [S].
TB 10501—98, Code for Environmental Protection Design of Railway Engineering[S].
[ 4 ] GB 50091—2006,铁路车站及枢纽设计规范 [S].
GB 50091—2006, Code for Design of Railway Station and Terminal[S].
[ 5 ] TB 10066—2000,铁路站场道路和排水设计规范 [S].
TB 10066—2000, Code for Design of Road and Drainage for Railway Station and Yard[S].
[ 6 ] GB 50090—2006,铁路线路设计规范 [S].
GB 50090—2006, Code for Design of Railway Line[S].
[ 7 ] 顾伟华. 上海城市轨道交通网络建设与资源共享 [J].城市轨道交通研究 , 2005 (6) : 15 - 19.
Gu Weihua. Construction and Resource Sharing of Shanghai URT Network[J]. Urban Mass Transit, 2005 (6) : 15 - 19.
[ 8 ] 董明峰. 上海城市轨道交通网络系统化建设的思考 [J].城市轨道交通研究 , 2006 (8) : 6 - 11.
Dong Mingfeng. On the Systematic Construction of Shanghai UMT Network[J]. Urban Mass Transit, 2006( 8) : 6 - 11.
[ 9 ] 朱军 ,宋键. 城市轨道交通资源共享探讨[J]. 城市轨道交通研究, 2003 (2) : 5 - 8.
Zhu Jun, Song Jian. How to share the Resources of Urban Mass Transit[J]. Urban Mass Transit, 2003(2) :5 -8.
[ 10 ] 朱沪生. 高质量 、高效率建设上海网络型枢纽型城市轨道交通 [ J ]. 城市轨道交通研究 , 2004 (4) : 1 - 5.
Zhu Husheng. The Development of a " Network-type and Pivotal" Urban Rail Transit in Shanghai[J].Urban Mass Transit, 2004(4) : 1 - 5.
|
|
|
|