DISCUSSION ON THE PROBLEMS ABOUT CONSTRUCTION OF BALLASTLESS TRACK IN THE PASSENGER DEDICATED RAIL- WAY LINE |
LI Xiao-he |
The Fourth Survey&Design Institute of China Railway |
|
|
Abstract Different from traditional ballast track, there are significant differences in the control of subgrade settlement, the structure of subgrade bed, the construction of transitional section, as well as general pre- evaluation when constructing ballastless track. In this paper, after investigating the techniques of the ballastless tracks used in the world, several key technical problems about constructing ballastless track under subgrades discussed, which includes the concept of residual settlement, the constitution of subgrade settlement, the standard and the measures on the control of subgrade settlement, the transmission of dynamic stress on subgrade bed, the design patterns and the length of transitional section, as well as the construction techniques on connecting different types of structures for the ballastless track. Besides, the evaluation standard and the approach to analyze subgrade settlement before construction studied in detail. Combining with previous work on several existing passenger dedicated railway line and referred to the data from international consultation about the design of transportation line, some helpful suggestions are proposed to guide the design and the construction of the ballastless track in the passenger dedicated railway line
|
Received: 15 September 2005
|
|
|
|
|
[1]铁道第三勘察设计院.CHI高速铁路工程设计咨询报告(终 稿)[R].2005.
[2]铁道科学研究院.客运专线无碴轨道铁路设计指南(报批 稿)[R].2005.
[3]铁建设[2004]157号,京沪高速铁路设计暂行规定[S].
[4]钱立新.世界高速铁路技术[M].北京:中国铁道出版社,2003.
[5]铁道科学研究院铁建所.高速铁路线桥结构与技术条件(标 准)研究总报告[R].1996.
[6]杨广庆等.高速铁路路基设计与施工[M].北京;中国铁道出 版社,1999.
[7] DB DS836,路基工程设计、施工与维护[S].
[8] Handbuch Erdbauwerke DER BANHNEN Eurailpress[M]. 2004.
|
|
|
|