Research on the Impact of Construction of Box Culvert Underpass the Existing Highway on Environment |
ZHANG Jian1, GAO X iu-mei1,HUANG Sheng-gen2 |
1. The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251, China; 2. China University of Geosciences, Wuhan, Hubei 430074, China |
|
|
Abstract Research purposes: How to control the disturbance impact of construction of box culvert underpass the highway on the surrounding environment is a key point for jacking construction ofbox culvert rapidly and safely. In the course of jacking construction of one box culvertwith super large section and many technical difficulties, in order to reduce disturbance to the normal traffic of the existing highway, the underpass technology ofpipe –roof was used. This paper analyzes the tested data in site and researches the law ofdisturbance impactof jacking construction ofbox culvert on the surrounding environment.
Research conclusions:(1) At the place of the same elevation with the box culvert axis, the soils in front of working face generate the biggest horizontal movements. (2) By monitoring the contact stresses between soil and the culvert wal,l the effort of grouting and the total jacking forces can be obtained. (3) The box culvertcan be jacked in along the design path by adjusting jacking forces. (4) The pore pressure is a sensitive and exactindex for monitoring the vibration of soil in the process of box culvert jacking.
|
Received: 07 August 2009
|
|
|
|
|
[1] Ropkins JW T, Allenby D. Jacked box tunneling creating large shallow openings beneath existing highways and rail-ways [C ] //In: Rapid Excavation and Tunneling Confer-ence. NewOrleans, United States: Society forMining, Met-allurgy and Exploration, 2003: 1235 -1246.
[2] 《公路施工手册》编委会.公路施工手册[M ].北京:人民交通出版社, 2000.
[3] 任宗军.既有线斜交框架中继间顶进施工技术[J].铁道工程学报, 2006(2): 33 -38.
[4] 夏明耀,曾进伦.地下工程设计施工手册[M ].北京:中国建筑工业出版社, 1999.
[5] 张群胜.铁路既有线桥涵基础及顶进施工关键技术方法分析[J].铁道工程学报, 2008(3): 33 -37.
[6] 肖世国,朱合华,夏才初,等.管幕内顶进箱涵顶部管幕承载作用的分析[J].岩石力学与工程学报, 2005(18):3355 -3359.
[7] 李名淦,周江天,岑冈.下穿机场跑道价幕法箱涵顶进的变形规律研究[J].特种结构, 2006(2): 78 -80.
[8] 魏纲,徐日庆,屠玮.顶管施工引起的土体扰动理论分析及试验研究[J].岩石力学与工程学报, 2004(3): 476 -482.
[9] 乐韵斐.大型地下箱涵液压同步顶进控制[J].流动传动与控制, 2007(2): 3 -6.
[10]何莲,刘灿生,帅华国.顶管施工的顶力设计计算研究[J].给水排水, 2001(7): 87 -89.
|
|
|
|