Research on the Existing Subway Station Structure Safety Affected by Foundation Pit Excavation |
MA Qian-ying1 , MAO Nian-hua2 , ziiAO Jun-hai1 , WANG Sheliang3 |
1 .Chang' an University,Xi’an,Shanxi. 710061,China;2. China Railway First Survey and Design Institute Group Co. Ltd,Xian, Shanxi. 710043,China; 3 Xian University of Architecture and Technology, Xi’an,Shanxi 710055,China |
|
|
Abstract Research purposes: During the process of subsequent property development on the existing station, the larger foundation pit excavation impacts on the subway station structure obviously. In order to guarantee the safety of metro operation,the paper analyses the characteristics of stress and stain of soil during foundation pit construction process by numerical simulation model,and studies the effect of foundation pit excavation on subway station structure,then evaluates the safety of subway station structure, at last, it gives some suggests for the project.
Research conclusions (1)The subsequent property development has a adversely influence for the close neighbor existing subway station structure and rail.(2)In the process of foundation pit excavation,the deformation mainly appears at the bottom of the foundation pit,it should make a reasonable construction scheme,and follow the time- space effect" principle,to avoid large soil excavation.(3)In the process of simulation,the influence to the subway station because of the foundation pit settlement is the local stress concentration,it need reasonable simplification on the key point of construction process,which could ensure the simulation accuracy and calculation completeness.(4)Intends to strengthen the deformation monitoring of the near subway station structure during the process of construction, which could ensure safe operation and construction smoothly.(5)According to the practical engineering for analysis, the study results in this paper can be applied in treatment of the influence of the existing subway structure because of the subsequent property development.
|
Received: 06 January 2014
|
|
|
|
|
[1]陈福贵,向红,“地铁+物业”模式的经济分析[J].铁 道工程学报,2013(2);109-112.
Chen Fugui,Xiang Hong. Economic Analysis of "Subway and Property" Mode[ J].Journal of Railway Engineering Society , 2013 (2) ;109-112.
[2]汤佐群,郑元旺.“地铁+物业”模式的项目前期工作策略研究[J].城市轨道交通研究,2013(5);33-35 ,40.
Tang Zuoqun,Zheng Yuanwang. Strategic Research of the Preparatory Work Based on "Subway+Property” Mode [ J ].Urban Mass Transit, 2013 ( 5 ) ;33-35 ,40.
[3]西安市人民代表大会常务委员会,西安市城市轨道交通条例[S].
Xi' an People' s Congress Standing Committee.. Xi' an Urban Rail Traffic Regulations [ S ].
[4]伍尚勇,杨小平,刘庭金.双侧深基坑施工对紧邻地铁隧道变形影响的分析[J].岩石力学与工程学报,2012(增1);3452-3458.
Wu Shangyong, Yang Xiaoping, Liu Tingjin. Analysis of Influence on Deformation of Adjacent Subway Tunnel Due to Bilateral Deep Excavations [ J ].Chinese Journal of Rock Mechanics and Engineering, 2012 ( S1);3452- 3458.
[5]许有俊,陶连金,李文博,等.地铁双线盾构隧道下穿高速铁路路基沉降分析[J].北京工业大学学报,2010 (12);1618-1623.
Xu Youjun, Tao Lianjin, Li Wenbo,etc. A Numerical Simulation Study on the Settlement Laws of the High- speed Railway's Sugared Induced by the Construction of Twin Shield Tunnel[J].Journal of Beijing University of Technology, 2010 (12 ) ;1618-1623.
[6] 曹振,雷斌,张丰功.黄土地区地铁下穿既有铁路的施工风险及其控制措施[J].城市轨道交通研究,2013 (4) ;49-53 , 76.
Cao Zhen , Lei Bin , Zhang Fenggong. Risk Analysis and Control Measures of Subway Construction beneath the Existing Railway in Loess Areas[J].Urban Mass Transit, 2013 ( 4 ) ;49-53 ,76.
[7]任建喜,李龙,郑赞赞,等.黄土地区地铁盾构下穿铁 路变形控制技术[J].铁道工程学报,2013(5);57-62, 111.
Ren Jianxi,Li Long, Zheng Zanzan, etc. Deformation Control Technology for the Loess Subway Shield Under -crossing Railway [ J ] .Journal of Railway Engineering Society , 2013 ( 5 ) ;57-62,111.
[8]李宁,顾强康,朱才辉,等.西安地铁二号线下穿古城 墙段地表沉降控制标准研究[J].岩石力学与工程学报, 2009(增2);3753-3761.
Li Ning , Gu Qiangkang , Zhu Caihui , etc. Research on Ground Sedimentation Criterion of Xi' an Line-2 Subway under Circumvallation [ J ].Chinese Journal of Rock Mechanics and Engineering, 2009(S2):3753- 3761.
[9]信息产业部电子综合勘察研究院置地.时代广场项目 岩土工程勘察报告[R].西安:信息产业部电子综合勘 察研究院,2012.
Ministry of Information Industry Institute of Comprehensive Survey. Zhi Di? Shi Dai Square Project Geotechnical Engineering Survey Report[R]. Xi' an ; Ministry of Information Industry Institute of Comprehensive Survey , 2012.
[10 ] JGJ 120-2012,建筑基坑支护技术规程[S].
JGJ 120-2012 , Technical Specification of Retaining and Protection for Building Foundation Excavations [ S ].
[11]YB 9258-97,建筑基坑工程技术规范[S].
YB 9258-97,Code for Technique of Building Foundation Pit Engineering [ S ].
|
|
|
|