Optimization of Numerical Method for Excavating Scheme for Large Underground Cavern |
DUAN Ya-gang |
China Railway First Survey and Design Institute Group Ltd,Xi ′an Shanxi 710043,China |
|
|
Abstract Research purposes: For the excavation of large underground cavern,it is necessary to determine the proper excavating scheme according to the section shape and geological conditions. Also it is necessary to work out the selection criteria for the scheme according to the actual construction situation for selecting the best scheme. In this paper, the introduction is given to the issues of the stability of the surrounding rock in construction of one large sectional underground cavern,the productions of the minimum damaged floor and the minimum maximum displace caused disturbance during excavation are taken as the the optimal principle,and the simulation calculations of the excavation sequences in the same section with two numerical methods are made for getting the optimal construction scheme.
Research conclusions:(1)For excavation of large underground cavern,the minimum plastic damaged area, the vault settlement and the convergence deformation of the side wall caused by excavation can be used as the criteria for judging the excavation scheme.(2)From the angle of reducing disturbance on the surrounding rock,the excavation scheme of cutting the exposure time of the final boundary of the cavern section,such as first excavation of the pilot tunnel and then excavation of whole section,is better than the excavation scheme of directly excavating the sectional profile.(3)For this project,the excavation scheme of excavation of multiple pilot tunnels is better than the traditional excavation scheme of excavation in layer. ( 4 ) This research result is available for the optimal selection of excavation scheme for excavation of section of the cavern.
|
Received: 09 January 2013
|
|
|
|
|
[1]谢和平,等.关于21世纪岩石力学发展战略的思考[J]. 岩土工程学报,1996(4):98-102.
Xie Heping,etc. The Develops Strategic Reflection of the Rock Mechanics On Twenty-first Century[J]. Chinese Journal Geotechnical Engineering, 1996(4):98-102.
[2]朱维申.能量耗散模型在大型地下洞群施工顺序优化分析中的运用[Jl.岩土工程学报,2004(3) :358 -361.
Zhu Weishen. Application of Energy Dissipation Model to Optimization of Construction Order for Large Underground Caverns[J].Chinese Journal Geotechnical Engineering , 2004 ( 3 ) : 358-361.
[3]徐干成.地下工程支护结构[M].北京:中国水利水电出 版社,2003.
Xu Gancheng. The Supporting Structure of Underground Engineering[M].Beijing: China Water Power Press, 2003.
[4]M. Caia , P. K. Kaisera , H. Moriokab , M. Minamib , T. Maejimab, Y. Tasakac, H. Kurosec. FLAC/PFC Coupled Numerical Simulation of AE in Large-scale Underground Excavations [ J ].International Journal of Rock Mechanics&Mining Sciences, 2006(9):222- 224.
[5]Siriwardane, Desai C S. Computational Procedures for Non-linear Three-dimensional Analysis with some Advanced Constitutive laws [ J ].Int. J. Num. Analysis Method in Geomech ,1983 ( 7 ) :143-171.
[6]师金锋,张应龙.超大断面隧道围岩的稳定性分析[J]. 地下空间与工程学报,2005(2):227-230.
Shi Jinfeng, Zhang Yinglong. FEM Analysis of Rock Stability on Super Section Tunnel [ J ].Chinese Journal of Underground Space and Engineering , 2005 ( 2 ) : 227- 230.
[7]Gnirk, P. F, Fossum, A. F. On the Formulation of Stability and Design of Design Criteria for Compressed Air Energy Storage in Hard Rock Caverns[J]. Proceedings of the Intersociety Energy Conversion Engineering Conference ,1979 ( 8 ) : 429-440.
[8]苏晓堃.隧道开挖数值模拟的围岩边界取值范围研究 [J].铁道工程学报,2012(2):107-110.
Su Xiaokun. Research on Choosing Boundary Range of Surrounding Rock in Numerical Simulation of Tunnel Excavation[J].Journal of Railway Engineering Society , 2005 ( 2 ) :107-110.
|
|
|
|