Discussion on Calculation Model for Lining Structure of Shield Tunnel |
DAI Zhi-ren |
China Railway First Survey and Design Institute Group Co. Ltd, Shaanxi, Xi'an 710043, China |
|
|
Abstract Research purposes:The compression spring calculation mode is commonly used for the arch bottom of the shield tunnel, but it lacks the theoretical support. The internal forces and the settlement deformation trend obtained with this model are less than and inconsistent with the real situation so as to make the safety factor over lower. In order to enforce the reliability and accuracy of lining structure design,the comparison and analysis of different calculation models are carried out,the fundamental reason for wide application of the compression spring calculation model is put foreward, and the reasonable calculation model is presented.
Research conclusions:(1 )The reaction force form of the foundation of the arch bottom of the tunnel is closely related to the displacement trend. When the arch bottom raises and deforms, the reacting force of the foundation is only composed of the counterforce,but when the arch bottom compressedly deforms,the reacting force is composed of the counterforce and the compression resistance of the foundation. (2 ) For the shield tunnel,the lining structure calculation model of reacting force on the arch bottom should be used and it can precisely reflect the load bearing characteristics and displacement trend,and overcome the security risk due to the insufficient safety factor. (3) The form of the reacting force on the arch bottom based on the displacement trend and the corresponding calculation model are put forward. (4) This research result can be applied in the shield tunneling project, mining project and open excavation subway station or subsurface excavation subway station.
|
Received: 13 October 2012
|
|
|
|
|
[1] 戴志仁.盾构隧道管片设计若干问题研究与探讨[J]. 铁道工程学报,2012(6) :65 -70.
Dai Zhiren. Study and Discussion on the Issues about Segment Design of Shield Tunnel [ J ]. Journal of Railway Engineering Society, 2012(6) :65 -70.
[2] 中铁第一勘察设计院集团有限公司.兰州市城市轨道交 通1号线一期工程总体设计[Z].西安:中铁第一勘察设 计院集团有限公司,2011.
China Railway Fist Survey and Design Institute Group Co. Ltd. The Overall Project Design of Lanzhou Metro Line 1 at the First Stage[ Z]? Xi * an: China Railway Fist Survey and Design Institute Group Co. Ltd, 2011.
[3] 何川,张建刚,苏宗贤.大断面水下盾构隧道结构力学特 性[M].北京:科学出版社,2010.
He Chuang, Zhang Jiangang, Su Zongxian. Structural Mechanical Characteristics of Underwater Shield Tunnel with Large Cross Section [ M ] ? Beijing : Science Press, 2010.
[4] 戴志仁.软土地区盾构隧道同步注浆机理与工程应用研 究[D].上海:同济大学,2010.
Dai Zhiren. Study on the Mechanism and Engineering Application of Simultaneous Backfill Grouting in Shield Tunneling in Soft Soils [ D ]. Shanghai: Tongji University, 2010.
[5] 张凤祥,朱合华,付德明.盾构隧道[M].北京:人民交通 出版社,2004.
Zhang Fengxiang, Zhu Hehua,Fu Deming. Shield Tunnel [M]. Beijing: China Communications Press, 2004.
[6] 王梦恕,等.中国隧道及地下工程修建技术[M].北京: 人民交通出版社,2010.
Wang Mengshu, etc. Tunnelling and Underground Engineering Technology in China [ M ]. Beijing : China Communications Press, 2010.
[7] 施仲衡,等.地下铁道设计与施工[M].西安:陕西科学 技术出版社,2006.
Shi Zhongheng,etc. Design and Construction of Underground Railway [ M ] ? Xi,an: Shaanxi Science and Technology Press, 2006.
[8] DGJ 08—11 一2010,地基基础设计规范[S].
DGJ 08—11~2010,Foundation Design Code[S].
[9] 陈勇.云岭隧道仰拱填充隆起变形的原因分析及处理对 策[J].中国西部科技,2012(2) :4 -8.
Chen Yong. Reason and Countermeasures for the Uplifting Deformation of Yunling Tunnel [ J ] ? Science and Technology of West China, 2012(2) :4 -8.
[10] 戴志仁.盾构隧道盾尾管片上浮机理与控制[J].中国 铁道科学,2013(1 ):59-66. Dai Zhiren. Study on the Mechanism and Control Principle of Upward Movements of Segments at the Rear of Shield Tail [ J], China Railway Science,2013 (1): 59-66.
|
|
|
|