Design and Study on No. 9 Single Turnout of 60 kg/m Rail of Urban Rail Transit |
LIU Dao-tong,CHENG Bao-qing, TIAN Miao-sheng |
The Third Railway Survey and Design Institute Group Corporation, Tianjin 300251,China |
|
|
Abstract Research purposes: The No. 9 turnout of 60 kg/m is usually used in urban rail transit s main track and auxiliary track. There are mainly two types of turnouts used in the urban rail transit, namely the turnouts with the straight switch rail and the curve switch rail. The turnout with straight switch rail is available for the siding speed of 30km/h and the turnout with curve switch rail is available for the speed of 35 km/h. In order to improve the service level, the turnout with curve switch rail is used in the new 一 built metro. But the turnout with curve switch rail has its disadvantage,such as the serious wear of the switch rail and many non 一 standard parts. In order to give the paly of the single turnout with straight switch rail, a new type of single turnout available for the siding speed of 35 km/h is presented in this paper, with the features of the simple structure and long service life.
Research conclusions : (1) This new type of single turnout of the 60 kg/m rail has the straight switch rail,straight frog, and circular curve, with the simple structure. (2) Two switch rails are symmetrical, and can be pulled flexibly.(3)This turnout is available for the siding speed of 35 km/h,with less maintenance. (4) This research result has obvious advantages in the mature technology, reliability and security, and it is available for the metro, light rail and trolley car.
|
Received: 20 March 2013
|
|
|
|
|
[1]GB 50157-2003,地铁设计规范[S].
GB 50157-2003,Code for Design of Metro[S].
[2]TB 10082-2005,铁路轨道设计规范[S].
TB 10082-2005, Code for Design of Railway Track [S].
[3]建标104 - 2008,城市轨道交通工程建设标准[S].
Construction Standard 104 - 2008, Construction Standard for Urban Rail Transit Engineering[S].
[4] TB/T2477-2006,铁路道岔的容许通过速度[S].
TB/T 2477-2006, The Tolerated Through Speed of Trains Running at Railway Turnout[S].
[5]GB 50299—1999,地下铁道工程施工及验收规范(2003 年版)[S].
GB 50299-1999, Code for Construction and Acceptance of Metro Engineering(Version 2003) [S].
[6]铁道部第三设计院.道岔设计手册[K].北京:人民铁道 出版社,1975.
The 3rd Railway Design Institute. Turnout Design Handbook[K]. Beijing: People’s Railway Press, 1975.
[7]刘语冰.道岔结构和设计[M].北京:人民铁道出版社, 1974.
Liu Yubing. Turnout Structure and design [ M ] ? Beijing: People’s Railway Press, 1974.
[8]于春华.轨道论文集[M].沈阳:沈阳出版社,2007.
Yu Chunhua. Track memoir [ M ]. Shenyang; Shenyang Publishing House,2007.
[9]于春华,刘道通.地铁3.4m线间距单渡线总体方案研究 [J]-铁道工程学报,2006(9) :68 -72.
Yu Chunhua, Liu Daotong. Research on Overall Program of Laying Single Crossover with 3.4m Distance between Centers of Lines for Metro [ J]. Journal of Railway Engineering Society, 2006(9) ;68 - 72.
[10]GB 50157—2003,地铁设计规范[S].
GB 50157一2003,Discussion about Some Items of Code for Design of Metro[S].
|
|
|
|