Study on Reinforcement Effect of Shield Tunnel Adjacent to Existing Pile Foundation with Churning Pile

KOU Xiao - qiang,YANG Jing - fang,YE Guo - liang,CAO Yong - hua

Journal of Railway Engineering Society ›› 2011, Vol. 28 ›› Issue (11) : 98-103.

PDF(1831 KB)
PDF(1831 KB)
Journal of Railway Engineering Society ›› 2011, Vol. 28 ›› Issue (11) : 98-103.

Study on Reinforcement Effect of Shield Tunnel Adjacent to Existing Pile Foundation with Churning Pile

  • KOU Xiao - qiang,YANG Jing - fang,YE Guo - liang,CAO Yong - hua
Author information +
History +

Abstract

Research purposes: The churning pile is commonly used for the key parts to reduce the influence of the shield construction on the adjacent building. Therefore,it is necessary to do the research on the reinforcement effect during the construction,the influences of the reinforcement on the stress and deformation of the existing building and the occurrence and development laws of the deformation of the building during the shield tunnel under - passing the exiting building.
Research conclusions: From the simulation of the process of the shield tunneling through the adjacent piles with the ANSYS and the comparison of the simulation result with the in - situ measured results,it was revealed that the main deformation of the piles was up floating and lateral banding. In the process of the excavation of the non - reinforced body by the churning pile,the maximum calculated and measured up floating value was 2 mm while the maximum lateral deformation volume was 5. 7 mm. From the analysis of the influence of the reinforcement by the churning pile on the deformation of the pile foundation,it was concluded the reinforcement by the churning pile could effectively cut the lateral deformation of the pile foundation during shield tunnelling. Concretely speaking,after reinforcement by the churning pile,the lateral deformation of No. 1 pile body was cut by 28. 5% and the lateral deformation of No. 2 pile body was cut by 42. 2%.

Key words

shield tunnel / adjacent construction / churning pile / numerical simulation

Cite this article

Download Citations
KOU Xiao - qiang, YANG Jing - fang, YE Guo - liang, et al. Study on Reinforcement Effect of Shield Tunnel Adjacent to Existing Pile Foundation with Churning Pile[J]. Journal of Railway Engineering Society, 2011, 28(11): 98-103

References

[1] 李围,何川. 盾构隧道近接下穿地下大型结构施工影响研究[J]. 岩土工程学报, 2006( 10) : 1277 - 1282.
Li Wei,He Chuan. Study on Construction Influence of Shield Tunnels Traversing Adjacently under Underground Large - scale Structure [J]. Chinese Journal of Geotechnical Engineering,2006( 10) : 1277 - 1282.
[2] 孙玉永,周顺华,等. 软土地区盾构掘进引起的深层位移场分布规律[J]. 岩石力学与工程学报,2009( 3) : 500 -506.
Sun Yuyong,Zhou Shunhua,etc. Distribution of Deep Displacement Field during Shield Tunneling in Soft - soil Areas[J]. Chinese Journal of Rock Mechanics and Engineering,2009( 3) : 500 - 506.
[3] Li T,Liu B,etc. Field Instrumentation and 3 - D Numerical Modeling on Two Adjacent Metro Shield Tunnels Beneath Tall Buildings[C]/ /Proceedings of the International Young Scholars ' Symposium on Rock Mechanics - Boundaries of Rock Mechanics Recent Advances and Challenges for the 21st Century,2008.
[4] 张志强,何川. 深圳地铁隧道邻接桩基施工力学行为研究[J]. 岩土工程学报, 2003( 2) : 80 - 83.
Zhang Zhiqiang,He Chuan. Study on the Mechanical Behaviour of a Metro Tunnel Construction Adjacent to Existing Pile Foundations in Shenzhen [J]. Chinese Journal of Geotechnical Engineering,2003( 2) : 80 - 83.
[5] Kim S H,Burd H J,etc. Model Testing of Closely Spaced Tunnels in Clay[J]. Geotechnique,1998( 3) :375 - 388.
[6] 兰宇,方勇,段绍和,等. 地铁盾构隧道侧穿锦江大桥施工的三维数值模拟[J]. 铁道工程学报, 2009( 3) : 79 - 83.
Lan Yu,Fang Yong,Duan Shaohe,etc. Numerical Similation for Construction of Metro Shield Tunnel Undercrossing Jinjiang Bridge[J]. Journal of Railway Engineering Society,2009( 3) : 79 - 83.
 
PDF(1831 KB)

2811

Accesses

0

Citation

Detail

Sections
Recommended

/