A Comparative Analysis of the Cradle Cantilever Casting and Large Segmental Support Cast - in - place Method

TENG Bing - jie

Journal of Railway Engineering Society ›› 2012, Vol. 29 ›› Issue (6) : 55-58.

PDF(378 KB)
PDF(378 KB)
Journal of Railway Engineering Society ›› 2012, Vol. 29 ›› Issue (6) : 55-58.

A Comparative Analysis of the Cradle Cantilever Casting and Large Segmental Support Cast - in - place Method

  • TENG Bing - jie
Author information +
History +

Abstract

Research purposes: The comparison of cradle cantilever casting method and large segmental Support Cast - in - place method just concerned about the period and construction cost ,while ignoring the difference of structure stress . The plane bar system model of the structure was formed by simulating cradle cantilever casting method and large segmental Support Cast - in - Place method. Analysis on the difference about mechanical characteristic of continuous beam provides references for practice.
Research conclusions:By comparing the results model analysis,the bending moment and shear of continuous beam are different in two construction method. Compared with the cradle cantilever casting method,using large segmental Support Cast - in - place method would reduce the negative moment ,increase positive moment of the beam and make the shear of mid - span increase,the shear of side span reduce.

Key words

cradle cantilever casting / support cast - in - place / bending moment / shear

Cite this article

Download Citations
TENG Bing - jie. A Comparative Analysis of the Cradle Cantilever Casting and Large Segmental Support Cast - in - place Method[J]. Journal of Railway Engineering Society, 2012, 29(6): 55-58

References

[1] 葛俊颖. 桥梁工程(上)[M]. 北京:中国铁道出版社, 2007.
Ge Junying. Bridge engineering[M]. Beijing:ChinaRailway Publishing House,2007.
[2] 范立础. 预应力混凝土连续梁桥[M]. 北京:人民交通出版社,1988.
Fan Lichu. Prestressed Concrete Continuous Beam Bridge[M]. Beijing:China Communications Press, 1988.
[3] 白苹. 分节段支架现浇预应力混凝土连续箱梁受力分析与监测[D]. 北京:北京交通大学,2010.
Bai Ping. Mechanical Analysis and Monitoring of Segmental Support Cast - in - place Prestressed Concrete Continuous Box Beam[D]. Beijing:Beijing Jiaotong University. 2010.
[4] 袁帅. 分段现浇大跨度预应力混凝土连续梁的探讨[J].中国水运,2009(5):206 -208.
Yuan Shuai. Discussion for Segmental Cast - in - situ Construction of Long - span Prestressed Concrete Continuous Beam [J]. China Water Transport,2009 (5): 206 -208.
[5] 董文德. 支架法分段现浇大跨度变截面连续箱梁施工技术[J]. 现代交通技术,2006(3):46 -49.
Dong Wende. Construction Techniques of Long Span Continuous Box girder Bridge with Variable Cross Section Cast - in - place by Bracket Method [J]. Modern Transportation Technology,2006(3):46 - 49.
[6] 洪宏兴. 移动贝雷支架逐孔分段现浇在桥梁施工中的应用[J]. 中国港湾建设,2000(2):46 -48.
Hong Hongxing. Use of Technique of Moving Bailey Trusses to Cast Concrete in - situ in Sections in Bridge Construction [J]. China Harbour Engineering,2000 (2):309 -312.
[7] 邱志峪. 客运专线现浇梁膺架施工方案探讨[J]. 铁道工程学报,2007(12):46 -48.
Qiu Zhiyu. Discussion on the Trestle Construction Program of Cast - in - place Girder for Passenger Dedicated Line[J]. Journal of Railway Engineering Society,2007(12):309 - 312.
 
PDF(378 KB)

3024

Accesses

0

Citation

Detail

Sections
Recommended

/