Study on Timing of Building Beijing——Shenyang High——speed Railway

LI Yong—jin

Journal of Railway Engineering Society ›› 2013, Vol. 30 ›› Issue (6) : 4-9.

PDF(498 KB)
PDF(498 KB)
Journal of Railway Engineering Society ›› 2013, Vol. 30 ›› Issue (6) : 4-9.

Study on Timing of Building Beijing——Shenyang High——speed Railway

  • LI Yong—jin
Author information +
History +

Abstract

Research purposes:According to the functional orientation of the Beijing—Shenyang High—speed Railway in the railway network and the network plan for passenger outgoing and incoming of the Shanhai Passage,this paper systematically studies the timing of building the Beijing——Shenyang High——speed Railway through the comprehensive analysis and prediction of total passenger transportation volume of outgoing and incoming of the Shanhai Pass,the reasonable functions of various railways,the annual adaptability and transportation efficiency of existing railways and the demands of regional economic and social development.Construction of high—speed railway takes long time with the larger amount of investment,and it has the big influence on the local economic and social developments,SO the decision—making process is very complicated.The adaptability analysis of the corridor and passenger traffic volume related to the railway network is the most basic data for the decision—making on the timing of building the railway,but it is not the only determining factor.In addition,the regional economic development,improvement of comprehensive efficiency of railway network and environment change caused by the construction also should be fully taken into account.The research methods and ideas on the timing of building the railway presented in this paper can be as the reference to the similar works.
Research conclusions:conclusions:(1)From the views of meeting the traffic demands of outgoing and incoming of the Shanhai Pass and optimizing the railway network structure,the railway construction should be complete by 2020 in order to relax the traffic pressure and improve the service quality of the passenger outgoing and incoming of the Shanhai Pass.(2)From the views of promoting the coordinated development of the regional economy and improving the construction environment,the railway construction can change the poor transport situations of Chengde,Chaoyang and Fuxin areas along the railway,develop and enrich the travel resources and maintain the closely economic exchange of Beijing and Shenyang with the surrounding areas,and it is crucial to promotion of the coordinated development of the regional economy.(3)From the view of the projectg economic benefits,the two rapid passenger corridors with large traffic capacity will be formed after building the railway and they can enhance the railway network flexibility because they have enough traffic capacity in the early days after railway building.The trains of the different grades can run to meet the demands of the different passengers to reflect the public welfare and basic features of the railway.(4)The research on the method for the timing of building the railway presented in this paper is available for planing and construction of the transportation infrastructure.

Key words

Beijing—shenyang high—speed railway / construction timing / research

Cite this article

Download Citations
LI Yong—jin. Study on Timing of Building Beijing——Shenyang High——speed Railway[J]. Journal of Railway Engineering Society, 2013, 30(6): 4-9

References

[1] 国务院.综合交通网中长期发展规划[z].北京:国务院,2007.
The State Council.Mid and Long Term Development Plan of Multi—modal Transport Network[Z].Beijing:The State Council,2007.
[2] 国务院.十二五综合交通规划[z].北京:国务院,2012.
The State Council.The Twelfth Five—year Comprehensive Transport Plan[Z]?Beijing:The State Council,2012.
[3] 黄民.铁路“十一五”发展战略研究[M]?北京:中国铁道出版社,2008.
Huang Min.Study on the Eleventh Five—year Railway Development Strategies[M].Beijing:China Railway Publishing House,2008.
[4] 国家发展改革委.关于新建北京至沈阳铁路客运专线项目建议书的批复[Z].北京:国家发展改革委,2009.
National Development and Reform Commission.Official Reply on Proposal of Beijing to Shenyang Passenger Dedicated Line Project[z]. BeUing: National Development and Reform Commission,2009.
[5] 中国国际工程咨询公司.关于新建北京至沈阳铁路客运专线可行性研究的咨询意见[R].北京:中国国际工程咨询公司,2010.
China National Engineering Consultancy Company.Advisory Opinion on Feasibility Study of Beijing to Shenyang Passenger Dedicated Line[R].Beijing:China National Engineering Consultancy Company, 2010.
[6] 耿敬春.客运专线动车组与普速客车间最小追踪间隔研究[J].铁道工程学报,2013(2):7—10.
Geng Jingchun. Research on Minimum Headway between EMU and Cmmon Passenger Train on Passenger Dedicated Line[J].Journal of Railway Engineering Society,2013(2):7—10.
[7] 铁道第三勘察设计院集团有限公司.东北地区铁路网规划[R].天津:铁道第三勘察设计院集团有限公司,2005.
The 3rd Railway Survey and Design Institute Group Corporation.Railway Network Plan of Northeast Area of China[R].Tianjin:The 3rd Railway Survey and Design Institute Group Corporation,2005.
[8] 铁道第三勘察设计院集团有限公司.辽中南城镇群城际铁路网规划[R].天津:铁道第三勘察设计院集团有限公司,2008.
The 3rd Railway Survey and Design Institute Group Corporation.Railway Network Plan of City Group of Central and South Area of Liaoning Province『R].Tianjin:The 3rd Railway Survey and Design InstituteGroup Corporation,2008.
[9] 铁道第三勘察设计院集团有限公司.承德地区铁路网规划[R].天津:铁道第三勘察设计院集团有限公司,2005.
The 3rd Railway Survey and Design Institute Group Corporation.Railway Network Plan of Chengde Area[R].Tianjin:The 3rd Railway Survey and DesignInstitute Group Corporation,2005.
[10] 铁道第三勘察设计院集团有限公司.新建北京至沈阳铁路客运专线可行性研究报告[R].天津:铁道第三勘察设计院集团有限公2009.
The 3rd Railway Survey and Design Institute GroupCorporation.Feasibility Study of Beijing to ShenyangPassenger Dedicated Line[R].Tianjin:The 3rd Railway Survey and Design Institute Group Corporation,2009.
 
PDF(498 KB)

5087

Accesses

0

Citation

Detail

Sections
Recommended

/