Research on the Risk Transmission in the Construction Stage of Urban Rail Transit Project |
LIU Weiqing, ZHANG Hao, XU Zhifen |
Shijiazhuang Tiedao University, Shijiazhuang, Hebei 050043, China |
|
|
Abstract Research purposes: A large number of participants, as well as the connections between them, constitute a network of project activity nodes in the process of urban rail transit project construction. The internal and external risk factors of the project interact with the activity nodes, and these factors conduct risk transmission along the links between nodes in the network, so the impact is difficult to control. Therefore, this research uses the infectious disease model of network transmission dynamics for reference, simulates the risk transmission mechanism, adjusts different parameters, and explores the changes of risk transmission speed and scope, so as to provide reference for construction managers to implement risk decision-making. Research conclusions: (1) Using the SIR warehouse model to simulate the risk transmission process of the active node network during the construction phase of urban rail transit projects, the results show that reducing the effective transmission rate or increasing the unit's successful elimination rate can effectively curb risk transmission. (2) When the actual risk conductivity is greater than 1, it means that the information carried by risk factors is uncertain for participants. Once a risk event occurs, passive solutions need to reduce or cut off the connection between participants and risk factors in time. Safe and reliable resources can replace materials with risk impact in time to avoid the collapse of the overall network. (3) When the actual risk conductivity is less than 1, it means that the risk factors are relatively complete and accurate for the participants. Participants can take proactive precautions. According to the risk factors that have been mastered, the risk management capability of each activity node in the construction phase of urban rail transit projects is improved, and project management systems and emergency plans are formulated to help participants affected by risks return to normal operation as soon as possible.
|
Received: 26 February 2021
|
|
|
|
|
[1] |
杨琳,王嘉君.基于复杂网络模型的城市综合管廊PPP项目风险传递过程研究[J].浙江大学学报:工学版,2020 (9):1666-1676.Yang Lin,Wang Jiajun.Risk Transfer Process in Urban Comprehensive Corridor PPP Project Based on Complex Network Model[J].Journal of Zhejiang University:Engineering Science,2020(9):1666-1676.
|
[2] |
陈辉华,李瑚均,户晓栋.地铁盾构掘进安全影响因素及事故致因模型[J].铁道工程学报,2020(5):87-92.Chen Huihua,Li Hujun,Hu Xiaodong.Safety Influential Factors and Accident Causation Model of Subway Shield Construction[J].Journal of Railway Engineering Society,2020(5):87-92.
|
[3] |
吴贤国,陈跃庆,张立茂,等.地铁工程施工安全监控预警管理及评价标准研究[J].铁道工程学报,2013(5):107-111.Wu Xianguo,Chen Yueqing,Zhang Limao,etc.Research on the Standards for Safety Monitoring and Forewarning Management Assessment in Metro Construction[J].Journal of Railway Engineering Society,2013(5):107-111.
|
[4] |
王兴鹏,雷书华,刘文梅.基于CBR的地铁工程事故应急决策方法研究[J].铁道工程学报,2018(9):104-109.Wang Xingpeng,Lei Shuhua,Liu Wenmei.Research on the Emergency Decision - making Method for the Safety Accidents in Subway Construction Based on CBR[J]. Journal of Railway Engineering Society,2018(9):104-109.
|
[5] |
徐青,何松,魏可可,等.基于复杂网络理论的地铁深基坑施工事故致因研究[J].安全与环境工程,2017(1):152-161.Xu Qing,He Song,Wei Keke,etc.Accident Causation in Construction of Subway Deep Foundation Pit Based on Complex Network Theory[J]. Safety and Environmental Engineering,2017(1):152-161.
|
[6] |
刘慧,杨乃定,张延禄,等.考虑企业风险感知的R&D网络风险传播建模与仿真[J].系统管理学报,2020(3):494-501.Liu Hui,Yang Naiding,Zhang Yanlu,etc.Modeling and Simulation of R&D Network Risk Propagation Considering Risk Perception of Enterprises[J]. Journal of Systems & Management,2020(3):494-501.
|
|
|
|