Discussion of Settlement Analysis Method for Mid - compressible Clay of High Speed Railway |
SUN Hong - lin,CHEN Shang - yong |
China Railway Siyuan Survey and Design Group Co. Ltd,Wuhan,Hubei 430063,China |
|
|
Abstract Research purposes: Alluvial mid - compressible clay on fluvial high terrace is widely distributed at the Being -Shanghai high speed railway,which has a characteristic of high natural strength. Generally,there is no stability problem of filling and it can meet the need of engineering with no strict requirement for settlement when it at natural condition or after shalow layer treatment. However,ballastless track in high speed railway has strict requirements for subgrade residual settlement; Furthermore,current theoretical methods for calculating total and residual settlement of this type of soil can not meet the design requirement. So,through analysis of the basic characteristics of foundation soil and in - suit filling experiment on natural ground of Beijing - Shanghai high - speed railway,the settlement analysis method of this type of soil is studied.
Research conclusions: Basic characteristics,especially strong structural characteristic and high yield strength characteristic of mid - compressible clay on fluvial high terrace are summarized in this paper. Deformation law of this kind of foundation soil under low loading level is analyzed; At last,different calculation methods are proposed to calculate different settlement,that is,elastic theory method and proportion of settlement - completion method based on elastic method can be used in total settlement and residual settlement calculation respectively. Generally speaking,after the load stable for 6 months,completion of the settlement ratio can be up to 90%.
|
Received: 02 September 2011
|
|
|
|
|
[1] TB 10621—2009,高速铁路设计规范( 试行) [S].
TB 10621—2009,Code for Design of High Speed Railway[S].
[2] 李小和. 客运专线路基地段铺设无砟轨道有关问题的探讨[J]. 铁道工程学报, 2005( 5) : 20 - 24.
Li Xiaohe. Discussion on Some Problems about Construction of Ballastless Track in the Passenger Transportation Line[J]. Journal of Railway Engineering Society,2005( 5) : 20 - 24.
[3] 铁道部第四勘测设计院. 软土地基试验研究文集[G].武汉: 中国地质大学出版社, 2001.
The Fourth Survey and Design Institute of Ministry of Railways. Soft Soil Ground Test Research Essays[G].Wuhan: China University of Geosciences Press, 2001.
[4] GB 50007—2002,建筑地基基础设计规范[S].
GB 50007—2002, Code for Design of Building Foundation[S].
[5] 中铁第四勘察设计院. 软土地基路桥设计参数试验研究总报告[R]. 武汉: 中铁第四勘察设计院, 2004.
China Railway Siyuan Survey and Design Institute.Road and Bridge Design Parameters Test and Research Report on Soft Soil[R]. Wuhan: China Railway Siyuan Survey and Design Institute,2004.
[6] 中铁第四勘察设计院. 合宁铁路膨胀土处治技术研究报告[R]. 武汉: 中铁第四勘察设计院, 2007.
China Railway Siyuan Survey and Design Institute.Expansive Soil Treatment Technology Research Report in He - Ning Railway[R]. Wuhan: China Railway Siyuan Survey and Design institute,2007.
[7] 顾晓鲁,钱鸿缙,刘惠珊,等. 地基与基础( 第三版) [M].北京: 中国建筑工业出版社, 2003.
Gu Xiaolu,Qian Hongjin,Liu Huishan,etc. Ground and Foundation ( The Third Edition) [M]. Beijing:China Architecture and Building Press,2003.
|
|
|
|