Analysis of the Displacement Controlling Value of Large Load Pile Foundation Substitution Works |
TU Qiang |
China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan 610031, China |
|
|
Abstract Research purposes: Pile foundation substitution is a difficult problem in foundation work and the displacement controlling is the key to the pile foundation substitution works. This paper introduces briefly the foundation substitution works under the Grand Merchandise Building in Shenzhen metro, and emphasizes the analysis of the displacement controlling.
Research conclusions: The displacement controlling value is obtained, and the maximum internal force under this value is precondition for substitution structure and dynamic monitoring during constructing.
|
Received: 21 January 2008
|
|
|
|
|
[1]GB 50007-2002,建筑地基基础设计规范[S].
[2]GB 50010-2002,混凝土结构设计规范[S].
[3]JGJ 3-2002,钢筋混凝土高层建筑结构设计与施工规程[S].
|
|
|
|