Preliminarily Exploration on the Function Mechanism of Prevention and Treatment of Rockbrust for Tunnel |
XU Xiang-dong |
China Railway Siyuan Survey and Design Group Co. Ltd, Wuhan, Hubei 430063, China |
|
|
Abstract Research purposes: This paper carried out simulations of several often used anti-rockburst methods by using the discrete element method in order to provide theoretical basis for anti - rockburst design and ensure the safety of tunnel construction.
Research conclusions :The numerical simulation results show that the rock softening method by spraying water onto the rock surface is to achive the stress reduction in surface rock by reducing the rock deformation modulus, and thus suitable only for rock mass with strong water absoption. The stress release method by drilling holes is to achieve stress migration from surface rock to inner rock by drilling holes on the walls, and more suitable for weak to stronger rockbursts. The stress release method by blasting behind the work face is,however, to achieve more tangential stress transferring from surface rock to inner rock by conducting advanced blasting, and thus most applicable to strong rockbursts.
|
Received: 01 July 2008
|
|
|
|
|
[1]谭以安.岩爆形成机理研究[J].水文地质与工程地质, 1989(1): 34-38.
[2]周德培,洪开荣.太平驿隧洞岩爆特征及防治措施[J]. 岩石力学与工程学报,1995, 19(2): 171-178.
[3]张咸恭,王思敬,张倬元,等.中国工程地质学[M].北 京:科学出版社,2000.
[4]宋岳.岩爆问题[J].天津地质学会志,1991, 9(3): 50 -55.
[5]Cundall,P. A. (1971) A computer model for simulating progressive large scale movements in blocky rock systems. Proc. Symp. Int. Soc. Rock Mechanics, Nancy, France, Vol. 1, paper no. II -8.
[6]Cundall, P. A. UDEC - A generalised distinct dement pro?gram for modelling jointed rock. Report PCAR -1 -80, Pe?ter Cundall Associates, U. S. Army,European Research Of?fice, London, Contract DAJA37 -79 -C -0548 (1980).
[7]关宝树.隧道工程施工要点集[M].北京:人民交通出版 社,2003.
|
|
|
|