Research on the Detection Method of CP Ⅲ Points Stability in Fine Adjustment of Ballastless Track |
XU Xiao-zuo, LIU Cheng-long , YANG You-tao |
Southwest Jiaotong University, Cheng du, Sichuan 610031,China |
|
|
Abstract Research purposes: Fine adjustment of ballastless back has become one of the key technologies in control survey for ballastless track construction. In fine adjustment of ballastless track, the stability of CP Ⅲ points which are involved in resection should be detected before three-dimensional strict adjustment of the resection station, and then remove the unstable CP Ⅲ points. How to detect the stability of CP Ⅲ points and analyze the stability judgement method of CPⅢpoints as well as its feasibility, and also put forward some suitable judgement standards, so as to make sure the high precision of ballastless track laying.
Research conclusions: The paper proposes the method about the stability detection of Control Points m,which uses the information provided after the early CP Ⅲ plane and elevation control network adjustment and the measured distance and height difference of every two CP Ⅲ points calculated by measured data of free station in fine adjustment of ballastless track,and then compares with known distance and height difference. Theoretical analysis and testing results both validate that the method is correct and can detect the stability of CP Ⅲ points in plane and elevation. So the method proposed in the paper can be widely used in the project.
|
Received: 03 June 2008
|
|
|
|
|
[1]南塘,无碴轨道[J].铁道建筑,2004 (7 ) :60.
[2]铁建设[2006]189号,客运专线无碴轨道铁路工程测量 暂行规定[S].
[3]刘中华.荷比高速铁路Rheda2000无碴轨道测量技术 [J].山西建筑,2007(18):347-348.
[4]贺挨宽.无碴轨道施工平面控制主要技术标准的研究 [J].铁道工程学报,2006(9):27-30.
[5]苏兴,赵代强,钱振地.长枕埋人式无碴轨道道床板精确 控制测量施工技术[J].铁道工程学报,2005(1) :98-101.
[6]武汉大学测绘学院侧量平差学科组.误差理论与测量平 差基础[M].武汉:武汉大学出版社,2003
[7]李瑞林.无碴轨道控制测量技术[J].铁道标准设计, 2007(8):5-8.
|
|
|
|