Analysis of Reason for Frost Damage and Frost Protection Measure for Fire Pipe Installed in Station Platform of High—speed Railway in North China |
HE Zhan—min,GU0 Lin,CHE Yue—long,WU Guo—hua |
The Third Railway Survey and Design Institute Group Corporation,Tianjin 30025 1,China |
|
|
Abstract Research purposes: As the exceptional cold wave occurs frequently in north China recently to cause the forst crack and leakage of the fire pipe installed in the station platform of high—speed milway,the fire equipments dont work efficiently.It is found in the investigation that the fire pipe installed in the platform is used only for hydrant with its ends connected with the water pipe for passenger train to form a parallel water supply pipeline network.When there is no water supply to passenger train,the water pressure in fire pipe is basically in equilibrium and the velocity of the water flow in fire pipe is low with a little heat exchange.Aiming at this problem,the discussion is made on the frost protection measure to wet or dry fire pipe system installed in platform of high—-speed railway in north China to provide the reference to design of fire—fighting system installed the platform of high—speed railway.
Research conclusions:The fire pipe installed in platform of hiIgh—speed railway in north China should be layed below the frost line of soil if possible.Otherwise,the frost protection measure should be taken to the wet or dry fire pipe system according the concrete local conditions.
|
Received: 09 September 2010
|
|
|
|
|
[1]TB 10621--2009,高速铁路设计规范[S].
TB 10621--2009,Code for Design of High Speed Railway[S].
[2]TB 10010---2008,铁路给水排水设计规范[S].
TB 10010--2008,Code for Design of Water Supply and Sewerage of Railway[S].
[3]TB 10063--2007,铁路工程设计防火规范[S].
TB 10063--2007,Code for Design on Fire Prevention of Railway Engineering[S].
[4]GB 50016--2006,建筑设计防火规范[S].
GB 50016--2006,Code for Design on Building fire Protection and Prevention[S].
[5]GB 50013--2006,室外给水设计规范[S].
GB 50013--2006,Code for Design of Outdoor Water Supply Engineering[S].
[6]杨泽厚.铁路工程设计技术手册:给水排水[K].北京:中国铁道出版社,2004.
Railway Engineering Technical Standards Handbook—Water Supply and Drainge Engineering[K].Beijing:China Railway Publishing House.2004.
[7] 常伯涛.自调控电伴热系统的原理和应用[J].安装,2000(1):1—2.
Chang Baitao.The Principle and Apply of Electric Heating of the Regulate System of Outside Temperature [J].Install,2000(1):1-2.
[8] 王军,张爱亭.地铁干式消火栓系统设计研究[J].消防科学与技术.2007(5):539—540.
Wang Jun,Zhang Aiting.The Fire Water—supply in Dry—wet System of Design Study on Subway[J].Fire Protection Science and Technology,2007(5):539—540.
[9] 张长国,喻岩,新型的管道防冻——电伴热保温施工技术[J].国防交通工程与技术,2005(2):61-63.
Zhang Changguo,Yu Yan.New Construction Techniques for the Freezing Prevention of Tubes—The Electrically Heating Construction Technology[J].National Defense and Technology,2005(2):61—63.
[10]潘大新,霍有利,吴磊.海上油气田平台消防水干湿式系统的选择[J].工业用水与废水,2007(2):95—97.
Pan Daxin,Huo Youli,Wu Lei.The Choose of Fire Water—supply in Dry-wet System on Offshore Platform[J].Industrial Water and Industrial Sewage, 2007(2):95—97.
|
|
|
|