Research on the Scheme for Leading Longkou-Yantai Railway into Yantai Region |
WANG Qing-hui1, SUN Zhao-wu1, WANG Gang2 |
1. Jinan Design Institute, China Railway Engineering Consultant Group, Jinan, Shandong 250022,China; 2. China State Construction Engineering Corp. Ltd, Beijing 100044, China |
|
|
Abstract Research purposes:This paper describes the existing railway profile and the general near-term and long-term railway plan of Yantai region, and researches the railway arrangement in Yantai region after leading Longkou-Yantai Railway into Yantai region for the purposes of enhancing the carrying capacity of the block section and reducing the cross interference among the tracks.
Research conclusions:With completions of Dezhou-Longkou Railway, Qingdao-Weihai Intercity Railway, Lancun-Yantai Electrified Railway and the second line of Dezhou-Longkou Railway and leading them into Yantai region in the near future or in future, the railway crossing pattern with two double -track main lines, one intercity railway and one double track feery railway will be formed in Yantai region. In the near future, the Longkou-Yantai Railway will be led into Fushan Station to remain Zhuji Block Postand drawn forth through the turnout 18 of Yantai-Daliang Feery Railway to connect with Yantai-Daliang Feery Railway and cross over the Lancun-Yantai railway in the middle part. After completion of the second track of Longkou-Yantai Railway in future, the Zhuji Sourth Railway Station will be built instead of Zhuji Block Post and it will have five main lines from the Longkou-Yantai Railway, the Yantai-daliang Ferry Railway and Lancun-Yantai Railway. Also the Longkou-Yantai Double-track Railway and Lancun-Yantai Single-track Railway will be led into the Zhuji Station.
|
Received: 25 December 2009
|
|
|
|
|
[ 1 ] GB 50091—2006,铁路车站及枢纽设计规范[S].
GB 50091—2006, Railway Station and Terminal Design Standards[S].
[ 2 ] 李朝阳.新建铁路青岛至荣成城际铁路可行性研究[Z]. 天津:铁道部第三勘察设计院, 2009.
Li Zhaoyang. Feasibility Research on Qingdao-Rongcheng Newly-built Railway [Z]. Tianjin: The Third Railway Survey and Design Institute Corporation,2009.
[ 3 ] 王庆辉.新建铁路龙口至烟台线可行性研究[Z ].北京: 中铁工程设计咨询集团有限公司, 2009.
Wang Qinghui. Feasibility Research on Longkou-Yantai Newly-built Railway[Z]. Beijing: China Railway Engineering Design & Consultant Group, 2009.
[ 4 ] 张沛艳.高速铁路站场设计几个问题的探讨[J].铁道 工程学报, 2008(10): 83 -86.
Zhang Peiyan. Discussion on the Design of High Speed Railway Station and Yard[J]. Journal of Railway Engineering Society, 2008(10): 83 -86.
[ 5 ] 谢海红,周浪雅,杨丽娟.铁路客运专线引入既有枢纽的方案选择[J].北京交通大学学报, 2008(3): 6 -10.
Xie Haihong, Zhou Langya, Yang Lijuan. Scheme Choice for Introducing Passenger Dedicated Line into Railway Hub[J]. Journal of Beijing Jiaotong University, 2008(3): 6 -10.
[ 6 ] 辛灵.客运专线引入枢纽相关问题研究[D].成都:西南交通大学, 2008.
Xin Ling. Study on Related Problems of Introducing Passenger Dedicated Line into Railway Terminal[D]. Chengdu: Southwest Jiaotong University, 2008.
[ 7 ] Ricardo Mateus, J. A. Ferreira, Joao Carreira. Multicriteria decision analysis (MCDA): Central Portohigh-speed railway statlon[J]. European Journal of Operational Research, 2008(187): 1 -18.
|
|
|
|