Study on Settlement Control of Dig Jet Mixing Pile Composite Foundation and Soft Rock Filling Embankment |
QING San-hui1,CAO Xin-wen2,XIE Qiang2 |
1. China Railway No.2 Engineering Group Co. Ltd., Chengdu, Sichuan 610031, China; 2. Southwest Jiaotong University,Chengdu, Sichuan 610031, China |
|
|
Abstract Research purposes:Application of geotechnical centrifugal model test verifies whether the post-construction settlement of the dig jet mixing pile composite foundation and soft rock filling embankment in red rock area can meet requirement of the designed control standard or not for the purpose of guiding the design and construction.
Research conclusions:The experiment done in the experimental section shows the compacting factor of soft rock filling material in red rock area shall be more than 0.93, and the tracks should be laid at least 6 months later after the embankment is filled. In this way, the post-construction settlement of top layer of the embankment of dig jet mixing pile composite foundation can meet requirement of the designed control standard, namely, the settlement is 15 cm and the settlement rate is 4 cm annually. The experiment also shows application of the dig jet mixing pile composite foundation with the distance between piles of 1.0 m and pile diameter of 50 cm and soft rock filling embankment is feasible, which is very significant to guiding the design and construction.
|
Received: 19 November 2009
|
|
|
|
|
[ 1 ] 杜延龄.土石坝离心模型试验研究[J]. 水利水电技术,1997(6):54 -58.
Du Yanling. Study on the Centrifugal Model Test for Earth-rock Dam[J]. Water Resources and Hydropower Engineering, 1997(6): 54 -58.
[ 2 ] 谢永利,等.应用离心模型试验研究软基变形性状[J]. 岩土工程学报, 1995(4): 45 -49.
Xie Yongli, etc. Study on Deformation Behavior of Soft Clay Ground with[J]. Chinese Journal of Geotechnical Engineering, 1995(4): 45 -49.
[ 3 ] 胡长明.深层搅拌桩挡土墙土工离心模拟试验研究[J]. 西安建筑科技大学学报, 1997(4): 463 -469.
Hu Changming. Geotechnical Centrifuge Model Tests of the Retaining Wall with Deep Mixing Piles[J]. Journal of Xi'an University of Architecture & Technology, 1997(4): 463 -469.
[ 4 ] 王年香,章为民.深层搅拌法加固码头软基离心模型试验研究[J].岩土工程学报, 2001(5): 634 -638
Wang Nianxiang, Zhang Weimin. Centrifuge Model Test of Pier Ground Improved by CDM Chinese[J]. Journal of Geotechnical Engineering, 2001 (5): 634 -638.
[ 5 ] 曾友金,等.软土质地区微型桩基础离心模型试验研究[J].岩土工程学报, 2003(2): 242 -245.
Zen Youjin, etc. Study on Centrifuge Model Tests of Minipile Foundation in Soft Soil[J]. Chinese Journal of Geotechnical Engineering, 2003(2): 242 -245.
[ 6 ] 杜建成,等.软土归一化本构关系的离心试验验证[J]. 四川大学学报(工程科学版), 2001(1): 20 -22.
Du Jiancheng, etc. Validation of the Normalized Constitutive Model of Soft Clay Using Contrlfuge Test[J]. Journal of Sichuan University (Engineering Science Edition), 2001(1): 20 -22.
|
|
|
|