Study on the Plane Layout of Hezhou Railway Station of Guizhou-Guangzhou Rapid-speed Railway |
HAN Chang-sheng, LI Jie, YAO Chuan-kai |
China Railway Eryuan Engineering Group Co. Ltd, Chengdu, Sichuan 610031,China |
|
|
Abstract Research purposes:Hezhou is the central city in the northeast of Guangxi Zhuang Autonomous Region. The Hezhou district station locates in the junction of Luoyang-Zhanjiang Railway and Guiyang-Guangzhou Railway. As the traction mode on these two railway lines is different and Hezhou station is a helper station of Guiyang-Guangzhou Railway, how to undertake cross-line traffic and reasonably arrange the locomotive waiting track is very important to the plane layout of Hezhou Railway Station.
Research conclusions:When leading newly built rapid-speed railway into the district station under construction, the technical standards of the track under construction, construction situation and operational demands of the station under construction should be well known. The waste engineering and design changes should be minimized. When the district station links with the lines of more than one direction, the station layout should be made in yards according to the line priority. If the cross-line traffic is needed in all directions, it is necessary to build the connecting line. Double-line condition should be reserved if the line under construction is a single-line railway.
|
Received: 01 December 2009
|
|
|
|
|
[ 1 ] 中铁二院工程集团有限责任公司,新建铁路洛湛线岑西至茂名段工程施工图[R ].成都:中铁二院工程集团有限责任公司, 2005.
China Railway Eryuan Engineering Group Co. Ltd. Construction Drawing for Cenxi-Maoming Section of Newly-built LuoZhan Railway[J]. Chengdu: China Railway Eryuan Engineering Group Co. Ltd.
[ 2 ] 中铁二院工程集团有限责任公司,新建铁路贵阳至广州线可行性研究[R ].成都:中铁二院工程集团有限责任公司, 2007.
China Railway Eryuan Engineering Group Co. Ltd. Feasibility Study on Newly-built Guiyang-Guangzhou Railway[R]. Chengdu: China Railway Eryuan Engineering Group Co.Ltd.
[ 3 ] 铁道第四勘察设计院.铁路工程设计技术手册#站场及枢纽[K].北京:中国铁道出版社, 2004. The Fourth Survey and Design Institute of China Railways. Railway Engineering Technical Manual -Station and Yard and Terminal[K]. China Railway Publishing House, 2004.
[ 4 ] 周晓斌.动车检修基地总平面布局的探讨[J]. 铁道运输与经济, 2009(5): 22-26.
Zhou Xiaobin. Discussion on General Plan Layout of EMU Inspection and Maintenance[J]. Railway Transport and Economy, 2009(5): 22 -26.
[ 5 ] 杨利华.新建贵广铁路引入都匀地区方案研究[J]. 铁道运输与经济, 2009(5): 30 -32.
Yang Lihua. Study on Leading-in Scheme for Newly -built GuiGuang Railway in Duyun Area[J]. Railway Transport and Economy, 2009(5): 30 -32.
[ 6 ] 刘世峰.铁路接轨站设计应考虑的因素[J]. 铁道运输与经济, 2007(增刊): 58-60.
Liu Shifeng. Factors to Be Considered in Design of Railway Junction Station[J]. Railway Transport and Economy, 2007(Supplement): 58-60.
[ 7 ] 刘军强.敦煌车站站场设计研究[J]. 铁道运输与经济,2007(增刊): 83-85.
Liu Junqiang. Study on Design of Dunhuang Station and Yard[J]. Railway Transport and Economy, 2007(Supplement): 83-85.
[ 8 ] 包维民.十字交叉型客运站布置图型研究[J]. 铁道运输与经济, 2007(增刊): 31-35.
Bao Weimin. Study on Layout of Criss-crossing Passenger Station[J]. Railway Transport and Economy, 2007(Supplement): 31 -35.
[ 9 ] 黄富强.南京站站场改造工程建设方案的分析与思考[J]. 上海铁道科技, 2005(6): 9 -10.
Huang Fuqiang. Analysis and Thoughts on Construction Plan of Nanjing Station and Yard Upgrading Engineering[J]. Shanghai Railway Science & Technology, 2005(6): 9 -10.
[ 10 ] 金武.浅谈蚌埠站站场改造施工方案[J]. 上海铁道科技, 2005(3): 31-32.
Jin W u. Discussion on Construction Plan for Station and Yard Upgrading in Bengbu Station[J]. Shanghai Railway Science& Technology, 2005(3):31-32.
|
|
|
|