Directional and Connectional Measurement Technology for Silo 3 of Liuyanghe Tunnel with Gyro |
YUAN Ren-ai, DU Qiang, LUO Tian-lang |
China Railway First Guop Co. Ltd, Xi′an, Shanxi 710054, China |
|
|
Abstract Research purposes:The Silo 3 of Liuyanghe Tunnel of Wuchang - Guangzhou Passenger Dedicated Line is about 51.03 m deep and the length of the construction area of silo 3 is about 1.5 km. The high measurement accuracy is required for linking up the two ends of the silo with the inclined shaft and exit separately due to small silo portal. Using one - shaft orientation or two - shaft orientation method, it is hard to operate with low measurement accuracy. In order to through connect the whole Wuchang - Guangzhou Passenger Dedicated line, the connectional measurement plan for the silo should be determined in accordance with the local geographical condition and the structural feature of the silo for smooth construction of the silo with high accuracy.
Research conclusions:Through comparison, it is determined to conduct the measurement jointly with lead - hammer meter and gyro. The measuring principle and procedure of this method are described. The directional measuring number of gyro is at lease not less than three times. Before doing so, the ground control net should be measured closely and at the same time one known side on ground should be chosen to measure the position angle between it and gyro. This position angle should be compared with the inversely calculated position angle and its measurement accuracy should be verified. The measurement result after the through connection of the line shows the measurement accuracy can meet the requirement of large section tunnel construction of passenger dedicated line.
|
Received: 04 November 2008
|
|
|
|
|
[ 1 ] 孙允武. 陀螺仪在竖井定向测量的应用 [ J ]. 吉林水利 ,2007 (7) : 37 - 38.
Sun Yunwu. Application of Gyroscope in the Directional silo Measure[ J]. Jilin Water Resources, 2007( 7) :37 - 38.
[ 2 ] 张万清 ,姜信吉. 红外测距仪在高程测量中的应用 [ J ].测绘通报 , 1999 (10) : 43 - 44.
Zhang Wanqing, Jiang Xinji. Application of Infrared Range Finder in Height Measure [ J]. Bulletin of Surve and Mapping, 1999( 10) : 43 - 44.
[ 3 ] 李晓红. 隧道新奥法及其量测技术 [M ]. 北京 :科学出版社 , 2002.
Li Xiaohong. Tunnel Construction by NATM ( New Austrian Tunnelling Method ) and Technique of Monitoring Measurement[M ]. Beijing: Science Press, 2002.
[ 4 ] 孟繁义 ,孙允武 ,王凤艳. 长大隧洞竖井测量技术·引松入长工程老爷岭隧洞的控制测量 [ J ]. 吉林水利 , 1997(12) : 6 - 8.
Meng Fanyi, Sun Yunwu, Wang fengyan. Technology of Control Survey in Silo of Long and Large - section Tunnel - Technology of Control Survey in Laoyeling Tunnel for Drawing Water from Songhuajiang River to Changchun[ J]. Jilin Water Resources, 1997( 12) :6 - 8.
[ 5] 常国锋 ,柴均刚 ,黄俊. 河东金矿井下导线测角误差与精度分析 [ J]. 有色金属 , 2009( 4) : 19 - 21.
Chang Guofeng, Chai Jungang, Huang Jun. Underground Wire Errors and Precision analysis in Hedong Gold Mine [ J]. Nonferrous Metals, 2009( 4) :19 - 21.
[ 6 ] 李金祥. 陀螺经纬仪和垂准仪在深竖井中的联系测量系统及应用 [ J ]. 铁道标准设计 , 2005 (9) : 94 - 95.
Li Jinxiang. Application of the Liasion and Measure System of the Gyroscope and the Perpendicular Machine in Deep Silo[ J]. Railway Standard Design, 2005( 9) : 94- 95.
|
|
|
|