ANALYSIS OF MEASURED STRESS ON SECTION OF CURVED CONTINUOUS BRIDGE CONSTRUCTED BY JACK-IN METHOD |
LI Cheng jun, ZHOU Shi-jun |
Bridge Research Office of Railway Architecture Research Institute of China Academy of Railway Sciences |
|
|
Abstract As the non-elasticity of slow concrete contraction distortion is shown by reinforcement meter, the concrete stress measured by reinforcement meter pre-buried inside main girder in construction of curved continuous bridge by jack-in method. This paper presents two calculation methods with deductiong influence by slow contraction distortion and special treating the influence on calculation of measured stress by slow distortion. The methods were applied in monitoring construction of one bredge and got good results.
|
Received: 20 June 2004
|
|
|
|
|
[1]JTJ 023—85,公路钢筋混凝土及预应力钢筋混凝土桥涵设计 规范[S].
[2]周履,陈永春.收缩徐变[M].北京:中国铁道出版社,1994.
[3]李旭升等.斜拉桥施工监控中混凝土应力换算方法[J].兰州: 铁道学院学报,2001,(6):49-52.
|
|
|
|