Abstract Research purposes: The surrounding engineering environment of Wuhan Yangtze River Tunnel is complicated, and the shield under-passing the existingWuhan -Jiujiang Railway is one of the difficult points in the project. For accurate analysis of the settlement of the railway caused by the shield underpass, this paper calculates the influence of the shield driving on the settlement of Wuhan -Jiujiang Railway with the classical Peck Method and finite elementmethod respectively and introduces the protective measures taken in the construction and the onsite monitoring situation to provide the reference to the similar projects.
Research conclusions:The on site monitoring resultof the settlement is greater than the calculation resul,t butitdoesnot affect the traffic safety of the railway. Due to the impact of train operation, the trough width and depth of surface settlementcaused by the under-passing railway are both greater than those of the adjacentPeace Road.
|
Received: 01 July 2009
|
|
|
|
|
[1] 吕培林,周顺华.软土地区盾构隧道下穿铁路干线引起的线路沉降规律分析[J].中国铁道科学, 2007 (2):12 -15.
[2] 刘建航,侯学渊.盾构法隧道[M ].北京:中国铁道出版社, 1991.
[3] 杜孔泽,严广艺.近距离盾构隧道下穿铁路沉降分析[J].山西建筑, 2005(14): 80 -81.
[4] 肖龙鸽,王超峰,赵运臣.大直径泥水盾构施工引起的地表沉降分析和对策[J].现代隧道技术, 2008(5): 50 -53.
[5] 曹剑峰,韦凯.软土地区盾构下穿铁路地表变形规律研究[J].甘肃科技, 2008(4): 111 -113.
[6] 肖广良.盾构在软土地层穿越既有铁路施工技术[J].隧道建设. 2008(3): 325 -329.
[7] 骆建军,张顶立,王梦恕.地铁施工沉降监测分析与控制[J].隧道建设, 2006(1): 10 -12.
[8] 刘洪洲.盾构施工对软土地层沉降影响综述[J].公路隧道, 2001(3): 5 -10.
|
|
|
|