Exploration on the Settlement Computation of Bridge Pile Foundation in Collapsible Loess Zone on Zhengzhou—Xi’an Passenger Dedicated Line |
BAI Qi—cheng |
China Railway Eryuan Engineering Group Co.Ltd,Chengdu,Sichuan 610031,China |
|
|
Abstract Research purposes: As the Sanmenxia—Linbao section of Zhengzhou—Xi’an Passenger Dedicated Line lies in the deep collapsible loess zone,the over—settlement of bridge pile foundation occur8 due to the negative friction resistance.No computing method for pile foundation settlement in collapsible loess zone is reported up to now,80 it is necessary to do the searches on the computing method for the settlement of the bridge foundation pile in collapsible loess gone to control the total settlement in design.
Research conclusions: (1)In the settlement computation of bridge pile foundation in collapsible loess zone,the influence of negative friction resistance should be considered.(2)In design,it is reasonable that the total settlement of not more than the specified value is adopted for controlling the settlement of bridge pile foundation.(3)For the bridges in collapsible loess zone along the railway from Sanmenxia to Linbao,adopting the modified code of railway bridge to compute the total settlement of pile foundation can control the design.(4)The modulus of compressibility of soil beneath the pile bottom is the main influence factor on settlement computation,so it must be preciously measured during prospecting.
|
Received: 08 July 2008
|
|
|
|
|
[1] 铁建设[2007]47号,新建时速300~350 km客运专线铁 路设计暂行规定[S].
[2] 中铁二院工程集团有限责任公司.湿陷性黄土地区桥梁 桩基的负摩阻力及沉降计算方法研究[R].成都:中铁二 院工程集团有限责任公司, 2005.
[3] GB 50007-2002,建筑地基基础设计规范[S].
[4] JGJ 94-2008,建筑桩基技术规范[S].
[5] TB 10002. 5-2005,铁路桥涵地基和基础设计规范[S].
[6] GB 50025-2004,湿陷性黄土地区建筑规范[S].
[7] 铁道第三勘察设计院.桥涵地基和基础[M ].北京:中国 铁道出版社, 2002.
[8] 袁明,杜岩.无碴轨道涵洞地基加固及沉降控制[J].铁 道工程学报, 2006(7): 59 -63.
|
|
|
|